Using the WBS in the Special window, an instance of a work package is:
A.Build house
B.Excavate
C.Prepare Foundation
D.B and C
E.None of the above
参考答案
更多 “ Using the WBS in the Special window, an instance of a work package is:A.Build houseB.ExcavateC.Prepare FoundationD.B and CE.None of the above ” 相关考题
考题
Using the WBS shown in the Special window, a typical work package would be:ASoftware developmentBSystems designCCodingDA, B, and CENone of the above.
考题
Using the situation stated in the Special window, what is the total variable costs for producing one widget?A . ¥1,020B . ¥1,010C . ¥1,015D . ¥20E . None of the above.
考题
Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A . Become worse, become worseB . Become worse, improvedC . Improved, increasedD . Improved, become worseE . None of the above are correct
考题
Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.A . Over, 16.66B . Under, 16.66C . Over, 10.0D . Under, 10.0E . None of the above.
考题
Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A . 1.1B . 0.9C . 0.956D . 1.15E . 0.869
考题
Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A . Element PB . Element QC . Element RD . Element SE . None of the above.
考题
Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A . Element PB . Element QC . Element RD . Element SE None of the above.
考题
Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:A . $19KB . $21KC . $26KD . $29KE . indeterminate
考题
Using the situation stated in the Special window, what is the cost performance index for Case #9?A . 1.1B . 1.91C . 0.83D . 1.2E . None of the above
考题
Using the diagram in the Special window, what is the probability that Alternative I will be adopted and completed below budget:A 1.4B 0.8C 0.2D 0.12E None of the above
考题
Using the possible loss outcomes shown in the Special window, find the expected (loss)A ¥0B ¥-1,300C ¥-2,000D ¥-3,000E None of the above
考题
101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A. Element PB. Element QC. Element RD. Element SE. None of the above
考题
102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A. Element PB. Element QC. Element RD. Element SE. None of the above
考题
103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A. 0.875B. 1.14C. 0.952D. 0.833E. 1.20
考题
106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A. Become worse, become worseB. Become worse, improvedC. Improved, increasedD. Improved, become worseE. None of the above are correct
考题
113 Using the possible profit and loss outcomes shown in the Special window, find the expected profit (loss)A. ($1000)B. $1000C. $2000D. $1200E. None of the above
考题
121 Using the WBS in the Special window, an instance of a work package is:A. Build houseB. ExcavateC. Prepare FoundationD. B and CE. None of the above
考题
124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?A. $1,020B. $1,010C. $1,015D. $20.00E. None of the above
考题
133 Using the WBS shown in the Special window, a typical work package would be:A. Software developmentB. Systems designC. CodingD. A, B, and CE. None of the above
考题
137 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:A. $19KB. $21KC. $26KD. $29KE. indeterminate
考题
● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at theA taskB level of effortC sub-taskD projectE work package
考题
● Which of the following can be tracked using the WBS?A timeB costC performanceD scopeE None of the above.
考题
● Using the WBS shown in the Special window, a typical work package would be:A Software developmentB Systems designC CodingD A, B, and CE None of the above.
考题
● Which of the following can result in misinterpretation of the statement of work?A Using imprecise language (i.e. nearly, approximately)B Mixing tasks, specifications, special instructions and approvalsC No pattern, structure or chronological orderD Wide variation in the size of tasks or details of workE All of the above
考题
● Using the WBS in the Special window, an instance of a work package is:A Build houseB ExcavateC Prepare FoundationD B and CE None of the above
考题
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package
考题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource
B.individual work load
C.work milestone
D.work package