网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
The difference between the BCWS and the BCWP is referred to as the:
A . Schedule variance
B . Cost variance.
C . Estimate of completion
D . Actual cost of the work performed
E . None of the above
参考答案
更多 “ The difference between the BCWS and the BCWP is referred to as the:A . Schedule varianceB . Cost variance.C . Estimate of completionD . Actual cost of the work performedE . None of the above ” 相关考题
考题
根据赢得值原理图,表明工作实际费用超支和实际进度提前的是( )。A.BCWP-ACWP0B.BCWP-ACWP0C.BCWP-ACWPO和BCWP-BCWS0D.BCWP-ACWPO和BCWP-BCWS0
考题
76 The computation for Cost Performance Index is:A. BCWP/ACWPB. BCWP-ACWPC. BCWP-BCWSD. ACWP/BCWPE. ACWP-BCWS
考题
158 The computation for Cost Performance Index is:A. BCWP/ACWPB. BCWP-ACWPC. BCWP-BCWSD. ACWP/BCWPE. ACWP-BCWS
考题
根据赢得值原理图,表明工程实际费用超支和实际进度提前的是( )。A.BCWP-ACIVP0和BCWP一BCWS0 B.BCWP-ACWP0和BCIVP-BCWS0 C.BCWP-ACWP0和BCWP一BCWS0 D.BCWP-ACWP0和BCWP-BCWS0
考题
关于BCWP-BCWS和BCWP-ACWP说法不正确的是( )A.BCWS为拟完工程预算费用曲线B.BCWP为已完工程实际费用曲线C.BCWP-BCWS为正值表示进度提前,为负值表示进度拖后D.BCWP-ACWP为正值表示低于预算,为负值表示超出预算
考题
已知某项目的费用偏差大于0,进度偏差小于0。那么已完工作实际费用(ACWP),计划工作预算费用(BCWS)和已完工作预算费用(BCWP)三个参数的关系为( )。A.BCWP>ACWP>BCWS
B.BCWS>BCWP>ACWP
C..BCWS>ACWP>BCWP
D.BCWP>BCWS>ACWP
考题
某工程施工,至某月的月末,出现了工程的费用偏差小于0、进度偏差大于0的状况,则该工程的已完工作实际费用(ACWP)、计划工作预算费用(BCWS)和已完工作预算费用(BCWP)的关系可表示为( )。A、BCWP>ACWP>BCWS
B、BCWS>BCWP>ACWP
C、ACWP>BCWP>BCWS
D、BCWS>ACWP>BCWP
考题
下面的选项中哪一个表示项目进度超期了()A.BCWP = 100 , BCWS = 120B.BCWS = 100 , ACWP = 120C.BCWP = 100 , ACWP = 120D.BCWS = 100 , BCWP = 120
考题
7、下面的选项中哪一个表示项目进度超期了()A.BCWP = 100 , BCWS = 120B.BCWS = 100 , ACWP = 120C.BCWP = 100 , ACWP = 120D.BCWS = 100 , BCWP = 120
热门标签
最新试卷