Warranty cost is an example of an _____ .

A . internal failure cost

B . appraisal cost

C . external failure cost

D . customer satisfaction cost

E . All of the above.


参考答案

更多 “ Warranty cost is an example of an _____ .A . internal failure costB . appraisal costC . external failure costD . customer satisfaction costE . All of the above. ” 相关考题
考题 141 To calculate the expected value of an outcome:A. divide the value of each outcome by its probability, then add the results.B. divide the value of the desired outcome by the value all possible outcomesC. multiply the value of each outcome by its probability, then add the resultsD. use linear regression to assess the expected value of the outcomeE. B and D only

考题 155 A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.A. Inventory control.B. Materials management.C. Procurement.D. All of the above.E. A and C only

考题 68 An acceptance control chart has limits that are based on the spec. limits for the product rather than limits which differentiate between random and assignable causes. Under which of the following circumstances should a QC manager consider this type chartA. When the engineering tolerance on a dimension greatly exceeds the natural dispersion of the manufacturing processB. When the number of samples outside the current control chart limits become too costly and cumbersome to investigate.C. When a process is subject to constant but stable tool wear.D. A and B.E. A and C

考题 要将职能组织和WBS元素联系起来,项目经理应该使用一个:( )A.WBS索引B.项目WBSC.成本帐目矩阵D.工作包分配索引

考题 100 Including the customer in the process of project planning is:A. Slow and counterproductive.B. Essential in the definition and documentation of project goals.C. Necessary, but of limited value.D. Unnecessary because project goals are defined in the proposal stage.E. None of the above

考题 76 The computation for Cost Performance Index is:A. BCWP/ACWPB. BCWP-ACWPC. BCWP-BCWSD. ACWP/BCWPE. ACWP-BCWS

考题 139 Which of the following are types of status reports?A. document, variance, trend and exceptionB. cost, trend, schedule and acquisitionC. cost, schedule, technical performanceD. analysis, cost, performance and scheduleE. All of the above

考题 146 An effective Project Manager does not share project _____ with the team members.A. VisionB. responsibilityC. solution to problemsD. accountabilityE. status

考题 高风险项目通常会受到高层管理的关注以及最为细致的审查,高风险项目的项目经理最大的顾虑是高层管理常常会: ( )A.妨碍或干预项目管理B.规避或否认项目潜在的风险C.给与资源配置低优先权D.在要求额外资源时支持项目

考题 过去,你在提交项目进展状况报告的时候喜欢甘特图 ,以为这种表比较容易看懂,即使是高级管理机构也不例外。项目办公室今天发布了一个新的程序要求项目经理准备里程碑表示每两个星期更新一次。里程碑表与条形表不一样,它显示了( )A.主要事件的开始和完成时间B.行为开始和结束日期C.活动预期的持续时间D.活动之间的依附性

考题 在以下哪种合同中,更容易进行合同范围变更?A、 固定价B、 固定价加激励费C、 成本加成本百分比D、 以上都不是