● Documented work authorization provide:

A a means of effective internal coordination of the project's activities.

B an audit trail of all work authorized from project initiation to completion.

C a means for communication of work activity between the project manager and the performing activities.

D All of the above

E A and B only.


参考答案

更多 “ ● Documented work authorization provide:A a means of effective internal coordination of the project's activities.B an audit trail of all work authorized from project initiation to completion.C a means for communication of work activity between the project manager and the performing activities.D All of the aboveE A and B only. ” 相关考题
考题 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:AThe project managerBThe functional managerCThe project sponsorDThe clientEAll of the above

考题 Documented work authorization provide:A.a means of effective internal coordination of the project's activities.B.an audit trail of all work authorized from project initiation to completion.C.a means for communication of work activity between the project manager and the performing activities.D.All of the aboveE.A and B only.

考题 The project life-cycle can be described as:A.project concept, project planning, project execution, and project close-out.B.project planning, work authorization, and project reporting.C.project planning, project control, project definition, WBS development, and project termination.D.project concept, project execution, and project reporting.E.All of the above.

考题 The most effective means of determining the cost of a project is to price out the _____.A . Work breakdown structure.B . Linear responsibility chart.C . Project charter.D . Scope statement.E . Management plan.

考题 198 The most effective means of determining the cost of a project is to price out the _____.A. Work breakdown structure.B. Linear responsibility chart.C. Project charter.D. Scope statement.E. Management plan

考题 167 The project life-cycle can be described as:A. project concept, project planning, project execution, and project close-out.B. project planning, work authorization, and project reporting.C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.E. All of the above

考题 171 Documented work authorization provide:A. a means of effective internal coordination of the project's activities.B. an audit trail of all work authorized from project initiation to completionC.a means for communication of work activity between the project manager and the performing activities.D. All of the aboveE. A and B only

考题 142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A. The project managerB. The functional managerC. The project sponsorD. The clientE. All of the above

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:A The project managerB The functional managerC The project sponsorD The clientE All of the above

考题 ● The document authorizing functional areas to charge against the project is the:A Work authorization formB Scope baselineC Project charterD Management planE Linear responsibility chart

考题 ● A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above.

考题 ● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen

考题 Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.A.reviewingB.estimatingC.auditingD.expecting

考题 ● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.(75)A.independent resourceB.individual work loadC.work milestoneD.work package

考题 ● The project life-cycle can be described as(72).(72)A.project concept, project planning, project execution, and project close-outB.project planning, work authorization, and project reportingC.project planning, project control, project definition, WBS development, and project terminationD.project concept, project execution, and project reporting

考题 The project life-cycle can be described as(72). A.project concept,project plannin9,project execution,and project close-out B.project planning,work authorization,and project reporting C.project planning,project control,project definition,WBS development,and project termination D.project concept,project execution,and project reporting

考题 The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

考题 Project(69)Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement

考题 The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned schedule B.less work was completed than was planned C.the cost overrun for work completed D.the cost under-run of performance to date

考题 The project life-cycle can be described as().A.project concept, project planning, project execution, and project close-out B.project planning, work authorization, and project reporting C.project planning, project control, project definition, WBS development, and project termination D.project concept, project execution, and project reporting

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE B:Project stakeholder management C:Project scope management D:Project cost management

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE B. Project stakeholder management C. Project scope management D. Project cost management

考题 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level. A.independent resource B.individual work loaD. C.work milestone D.work package

考题 Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource B.individual work load C.work milestone D.work package

考题 Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement