24 A comparison of completion status to baseline is referred to as _____.

A. Earned value measurement.

B. Percent complete.

C. ACWP.

D. BCWS

E. None of above


参考答案

更多 “ 24 A comparison of completion status to baseline is referred to as _____.A. Earned value measurement.B. Percent complete.C. ACWP.D. BCWSE. None of above ” 相关考题
考题 Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:A.Variance reportsB.S curvesC.Trend analysisD.Earned value reportingE.Baseline control

考题 A comparison of completion status to baseline is referred to as _____.A.Earned value measurement.B.Percent complete.C.ACWP.D.BCWSE.None of above.

考题 Activities with zero time duration are referred to as:A.Critical path activites.B.Noncritical path activities.C.Slack time activities.D.DummiesE.None of above.

考题 The ability to achieve cost savings is inversely proportional to _____.A.the earned value achieved to dateB.the estimated costs to completeC.empowerment to the P.M.D.productivityE.None of the above.

考题 A budget estimate should give the manager cost data accurate to within:A . -5 to +10 percent of actual costB . -25 to +75 percent of actual costC . -30 to +75 percent of actual costD . -10 to +25 percent of actual costE . None of the above

考题 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

考题 The difference between the BCWS and the BCWP is referred to as the:A . Schedule varianceB . Cost variance.C . Estimate of completionD . Actual cost of the work performedE . None of the above

考题 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A . Become worse, become worseB . Become worse, improvedC . Improved, increasedD . Improved, become worseE . None of the above are correct

考题 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.A . Trend line.B . Trend analysis.C . S curve.D . Percent completion report.E . Earned value report.

考题 142 Activities with zero time duration are referred to as:A. Critical path activites.B. Noncritical path activities.C. Slack time activities.D. DummiesE. None of above

考题 58 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.A. Trend line.B. Trend analysis.C. S curve.D. Percent completion report.E. Earned value report

考题 18 The difference between the BCWS and the BCWP is referred to as the:A. Schedule varianceB Cost variance.C. Estimate of completionD. Actual cost of the work performedE. None of the above

考题 23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 46 Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called: A. Variance reportsB. S curvesC. Trend analysisD. Earned value reportingE. Baseline control

考题 105 A budget estimate should give the manager cost data accurate to within:A. -5 to +10 percent of actual costB. -25 to +75 percent of actual costC. -30 to +75 percent of actual costD. -10 to +25 percent of actual costE. None of the above

考题 183 Configuration (baseline) control monitors performance against theA. scope baselineB. original scheduleC. original budgetD. All of the above.E. None of the above

考题 100 The difference between the BCWS and the BCWP is referred to as the:A. Schedule varianceB. Cost variance.C. Estimate of completionD. Actual cost of the work performedE. None of the above

考题 105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB. Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 24 Activities with zero time duration are referred to as:A. Critical path activites.B. Noncritical path activities.C. Slack time activities.D. DummiesE. None of above

考题 106 A comparison of completion status to baseline is referred to as _____.A. Earned value measurement.B. Percent complete.C. ACWP.D. BCWSE. None of above

考题 48 The ability to achieve cost savings is inversely proportional to _____.A. the earned value achieved to dateB. the estimated costs to completeC. empowerment to the P.M.D. productivityE. None of the above

考题 106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A. Become worse, become worseB. Become worse, improvedC. Improved, increasedD. Improved, become worseE. None of the above are correct

考题 ● Configuration (baseline) control monitors performance against theA scope baselineB original scheduleC original budgetD All of the above.E None of the above.

考题 ● Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:A Variance reportsB S curvesC Trend analysisD Earned value reportingE Baseline control

考题 Which statement is true about the plan being loaded into the SQL baseline by the above command?() A. It is loaded with the FIXED status.B. It is loaded with the ACCEPTED status.C. It is not loaded with the ENABLED status.D.It is not loaded with the ACCEPTED status.

考题 Upon completion of fueling a gasoline driven vessel it is necessary to ______.A.keep ports,doors,windows,and hatches closedB.start engines immediatelyC.ventilate before starting engineD.None of the above

考题 Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulity B.risk C.change D.cost