The most expensive phase of life cycle costing is ( ) .

A.Termination
B.Applied research
C.Production
D.Operations and support

参考答案

参考解析
解析:
更多 “The most expensive phase of life cycle costing is ( ) .A.Termination B.Applied research C.Production D.Operations and support ” 相关考题
考题 Which of the following are included in the Acquisition phase(s) of the project life cycle.A . concept and developmentB . development and planningC . execution and phase-outD . planning and implementationE . concept and planning

考题 Feasibility studies occur in which life cycle phase (s)?A.ConceptualB.Conceptual or DevelopmentC.ExecutionD.Preliminary planningE.any life cycle phase

考题 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A.ConceptualB.Development.C.ExecutionD.FinishE.All of the above.

考题 QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A . 5%B . 10%C . 15%D . 25%E . 50%

考题 Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above

考题 The most expensive phase of life cycle costing is:A . R D.B . Applied research.C . ProductionD . Operations and support.E . Termination.

考题 Life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. Life cycle costing categories include the cost of _____, _____, and _____.A . R D, maintainability, operation and support.B . R D, production, operation and support.C . Acquisition, operations, maintenance.D . Production, operations, maintenance.E . None of the above

考题 During which phase of the project life cycle is the amount at stake lowest?A conceptB developmentC executionD conclusionE C and D

考题 74 Life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. Life cycle costing categories include the cost of _____, _____, and _____.A. R D, maintainability, operation and support.B. R D, production, operation and support.C. Acquisition, operations, maintenance.D. Production, operations, maintenance.E. None of the above

考题 189 The most expensive phase of life cycle costing is:A. R D.B. Applied research.C. ProductionD. Operations and support.E. Termination

考题 67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. ConceptualB. Development.C. ExecutionD. FinishE. All of the above

考题 141 Feasibility studies occur in which life cycle phase (s)?A. ConceptualB. Conceptual or DevelopmentC. ExecutionD. Preliminary planningE. any life cycle phase

考题 194 During which phase of the project life cycle is the amount at stake lowest?A. conceptB. developmentC. executionD. conclusionE. C and D

考题 6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB Development of design phaseC. Execution phase.D. Termination phase.E. None of the above

考题 185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above

考题 88 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phaseB. Development of design phaseC. Execution phase.D. Termination phase.E. None of the above

考题 82 Which of the following are included in the Acquisition phase(s) of the project life cycle.A. concept and developmentB. development and planningC. execution and phase-outD. planning and implementationE. concept and planning

考题 67 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above.

考题 ● Feasibility studies occur in which life cycle phase (s)?A ConceptualB Conceptual or DevelopmentC ExecutionD Preliminary planningE any life cycle phase

考题 ● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.A ConceptualB Development.C ExecutionD FinishE All of the above.

考题 The stages within the development phase of the software life cycle are ( 71 ).A.design, analysis, implementation, and testingB.analysis, design, implementation, and testingC.analysis, design, testing, and implementationD.design, analysis, testing, and implementation

考题 The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().A.developmentB.conceptC.system analysisD.implementation

考题 The following statements have been made about life cycle costing:(i) It focuses on the short-term by identifying costs at the beginning of a product’s life cycle(ii) It identifies all costs which arise in relation to the product each year and then calculates the product’s profitability on an annual basis(iii) It accumulates a product’s costs over its whole life time and works out the overall profitability of a product(iv) It allocates costs to each stage of a product’s life cycle and writes them off at the end of each stageWhich of the above statements is/are correct?A.(i) and (iii)B.(iii) onlyC.(i) and (iv)D.(ii) only

考题 Which of the following statements is correct?A.The definition phase results in the Software Requirements Specification.B.Testing is optional in software life cycle.C.CASE tools can only aid in the design phase of a software life cycle.D.A change during a later phase does not require the documentation of all earlier phases to be updated.

考题 The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopment B.concept C.system analysis D.implementation

考题 The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.development B.concept C.system analysis D.implementation

考题 The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ). A.development B.concept C.system analysis D.implementation