( )is a process of developing a detailed description of the project and product
A.collect requirements
B.Scope definition
C.validate scope
D.Control range
B.Scope definition
C.validate scope
D.Control range
参考答案
参考解析
解析:范围定义是一个详细描述项目和产品的过程
更多 “( )is a process of developing a detailed description of the project and productA.collect requirements B.Scope definition C.validate scope D.Control range ” 相关考题
考题
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend
考题
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend
考题
( ) describes, in detail, the project s deliverables and the work required to create those deliverables.A.Product scope description B.Project objectives C.Product specification D.The project scope statement
考题
Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object
考题
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project
考题
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。A、Validate scopeB、Define scopeC、Control scopeD、Collect requirement
考题
It can be inferred from the passage that in artistic creation______.A.product is more important than processB.process is more important than productC.process and product are equally importantD.both process and product are unimportant
考题
● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.(75)A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis
考题
Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.A.communicatingB.collectingC.filingD.documenting
考题
(接上一题)It is a(2)process throughout a project. A requirement is a capability to which aproject outcome(product or service)should conform.A.persistentB.continuingC.permanentD.continuous
考题
Plan Quality is the process of identifying quality requirements and standards for the project and product and documenting how the project will demonstrate compliance ______ is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement and failing to meet requirements.A.Cost-Benefit analysisB.Control chartsC.Quality function deploymentD.Cost of quality analysis
考题
The features and functions that characterize a product,service,or result in a project are called( )A.statement of workB.product scopeC.product qualityD.project scope
考题
()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.A.The project charterB.The project scope statementC.The WBS dictionaryD.The activity list
考题
( )is a process of developing a detailed description of the project and productA.collect requirements
B.Definition scope
C.validate scope
D.Control range
考题
()describees,indetail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Produce specification
D.The project scope statement
考题
( )is a process developing a document that formally authorizes the existence of a project and provides the
project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter
B.Manage Project Knowledge
C.Monitor and Control Project work
D.Close project
考题
( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
考题
Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement
B.statement of work
C.project management plan
D.project policy
考题
( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter
B.Manage Project Knowledge
C.Monitor anD.Control Project work
D.Close project
考题
Requirements management is a ( ) process throughout a project.A requirement is a capability to which a project outcome(product or service)should conform. A.persistent
B.continuing
C.permanent
D.continuous
考题
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy
考题
Which design phase service component consists of developing a detailed, site-specific plan for implementing a new technology system or solution? Select exactly 1 answer(s) from the following:()。A、Detailed Design DevelopmentB、Systems Acceptance Test Plan DevelopmentC、Staging PlanD、Implementation Plan DevelopmentE、Project Kick-off
考题
Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A、performanceB、processC、productD、object
考题
What is a reason for reviewing the user requirements document with the client?()A、To gain the client’s acceptance of the detailed designB、To verify mutual understanding of project resourcesC、To verify mutual understanding of the detailed project planD、To verify mutual understanding of targeted product performanceE、To verify mutual understanding of the tests that will be done after the product is completed
考题
单选题What is a reason for reviewing the user requirements document with the client?()A
To gain the client’s acceptance of the detailed designB
To verify mutual understanding of project resourcesC
To verify mutual understanding of the detailed project planD
To verify mutual understanding of targeted product performanceE
To verify mutual understanding of the tests that will be done after the product is completed
考题
单选题Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A
performanceB
processC
productD
object
考题
单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A
analyzeB
trackC
levelD
extend
考题
单选题analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a()process throughout a project. A requirement is a capability to which a project outcome(product or service)should conform.A
persistentB
continuingC
permanentD
continuous