Software configuration management(SCM)is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification,change control, ( ) and configuration audit.
A.milestones marking
B.status reporting
C.stakeholder management
D.quality audit
B.status reporting
C.stakeholder management
D.quality audit
参考答案
参考解析
解析:软件配置管理(SCM)是一种跟踪和控制软件的变化的技术。配置管理包括配置标识、变更控制、状态报告和配置审计。
更多 “ Software configuration management(SCM)is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification,change control, ( ) and configuration audit. A.milestones marking B.status reporting C.stakeholder management D.quality audit ” 相关考题
考题
The purpose of configuration management is to:A.insure drawings are updatedB.control change throughout the projectC.control change during the production onlyD.generate engineering change proposalsE.inform. the project manager of changes
考题
33 The purpose of configuration management is to:A. insure drawings are updatedB. control change throughout the projectC. control change during the production onlyD. generate engineering change proposalsE. inform. the project manager of changes
考题
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
A.RationalClearcaseB.QualityFunctionDeploymentC.VisualSourceSafeD.ConcurrentVersions System
考题
● Project life cycles are very useful for _____ and _____ .A Configuration management, terminationB Objective setting, information gatheringC Standardization, controlD Configuration management, weekly status updatesE Approval, termination
考题
● The purpose of configuration management is to:A insure drawings are updatedB control change throughout the projectC control change during the production onlyD generate engineering change proposalsE inform. the project manager of changes
考题
● Configuration management is the process of managing change in hardware, software, firmware, documentation, measurements, etc. As change requires an initial state and next state, the marking of significant states within a series of several changes becomes important. The identification of significant states within the revision history of a configuration item is the central purpose of (75) identification.(75)A. baselineB. valueC.costD. control
考题
● Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.(74)A.Rational ClearcaseB.Quality Function DeploymentC.Visual SourceSafeD.Concurrent Versions System
考题
● __(73)__ are the four major activities of software configuration management.①configuration identification ②statement report ③change control④preparation of requirement document ⑤configuration auditing(73)A.①②③④ B.①②④⑤ C.①②③⑤ D.②③④⑤
考题
Software configuration management(SCM) is the task oftracking and controlling changes in the software. Configuration managementpractices include configuration identification,change control ,(74)and configuration audit.A.milstones markingB.status reportingC.stakeholder managementD.quality audit
考题
Configuration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes important.The identification of significant states within the revision history of a configuration item is the central purpose of(75) identification.A.baselineB.valueC.costD.control
考题
Software configuration management(SCM),is the task of tracking and controiling changes in the software,configuration management practicesconfiguration identirication change control ()and configuration auditA.ailestones markingB.status reportingC.stakeholder managementD.quality audit
考题
Network management helps you to(66)the strengths and weaknesses of your network, as well as determine any configuration changes that may be necessary. Any controlled changes to your network and its components-especially configurations, software and(67), can have an effect on its overall efficiency. To maintain control, you need the tools and knowledge to manage all activity that has the potential to affect your(68).A.seeB.knowC.monitorD.control
考题
The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)A.change control boardB. project management officeC.project managerD.configuration management officer
考题
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer
考题
()are the four major activities of software configuration management.①configuration identification ②statement report③change control④preparation of requirement document ⑤configuration auditing
A.①②③④
B.①②④⑤
C.①②③⑤
D.②③④⑤
考题
Configuration management is focused on the specification of both the deliverables and the processes;while( )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.A.cost management
B.change management
C.configuration management
D.capacity management
考题
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes. ( ) is not a project configuration management tool.A.Rational Clearcase
B.Quality Function Deployment
C.Visual SourceSafe
D.Concurrent Versions System
考题
( ) is the process of documenting. Analyzing,tracing,prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project. A.Integrated management
B.Configuration management
C.Scope management
D.Requirements management
考题
In the operate phase, providing and maintaining reliable, current information about the WLANsystem hardware, software, and applications pertinent to the system’s individual components andattributes is part of which service component?()A、Problem ManagementB、Configuration ManagementC、Incident ManagementD、Change Management
考题
( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.A、Integrated managementB、Configuration managementC、Scope managementD、Requirements management
考题
Software configuration management (SCM) is the task of tracking and controlling changes in the software. Configuration management practices include configuration identification, change control, ( ) and configuration audit.A、milestones markingB、status reportingC、stakeholder managementD、quality audit
考题
Which statement correctly describes the change tracking writer (CTWR) background process?()A、 It keeps track of changes in the background processes.B、 It records the system change number (SCN) in the control file.C、 It writes audit records for user changes to the change tracking file.D、 It records any changes to the listened configuration in the listener.ora file.E、 It records any changes to the database parameters in the change tracking file.F、 It records the physical location of all the changes that are made to the database in the change tracking file.
考题
In the past several months, manual intervention has been required to correct improper cluster configuration changes. The administrator received a directive from management to create a more effective strategy for making the changes required fro month-end processing. How can HACMP be used to meet the requirements of management’s directive?() A、 Create a snapshot for each of the required cluster configurations.B、 Create a custom snapshot method to handle the configuration changes.C、 Create a custom verification method to verify configuration changes.D、 Create a cluster custom event to mange required configuration changes.
考题
In the operate phase, providing and maintaining reliable, current information about the wlan system hardware, software,and applications pertinent to the system’s individual components and attributes is part of which service component?()A、problem managementB、configuration managementC、incident managementD、change management
考题
Configuration Management controls what? 配置管理控制什么?()A、Auditing and controlling any changes to the Trusted Computing Base. 审计和控制对可信计算基的任何更改B、Auditing of changes to the Trusted Computing Base. 审计可信计算基的变更C、Control of changes to the Trusted Computing Base. 控制可信计算的变更D、Changes in the configuration access to the Trusted Computing Base. 对可信计算基配置访问的变更
考题
多选题Which three statements describe the configuration change management feature in DCNM LAN? ()ASwitch profiles allow configurations to be synchronized between switches and are supported with any Cisco NX-OS Software managed device.BDCNM LAN can archive configurations from devices even if they are not managed by the DCNM server, and the administrator can supply the device management IP address and credentials.CYou can archive a maximum of 50 configuration versions per managed device.DManaged devices must be licensed in DCNM LAN before they can be used with configuration change management.EDevice-running configuration will be archived only if it differs from the last archived version.
考题
单选题Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.A
RationalClearcaseB
QualityFunctionDeploymentC
VisualSourceSafeD
ConcurrentVersions System