应届毕业生首次报考ACCA考试注意事项有哪些?

发布时间:2020-02-28


近年来ACCA考试热度不断上升,在社会上日渐受到关注,更多的应届毕业生也加入到ACCA的考试大军当中。比如,有网友就表示自己是首次报考ACCA的应届毕业生,想问下需要注意哪些地方。鉴于此,51题库考试学习网在下面为大家带来有关2020ACCA考试报名方法的相关情况,以供参考。

首次报考ACCA考试,需要想成为ACCA注册学员,这一点是首次报考人员需要注意的地方。申请注册方法分为代注册以及官网注册两种,小伙伴们可自行选择。

下面是具体注册流程:

首次申请注册ACCA学员可采取网上注册以及代注册方式。网上注册需要在ACCA官网申请,并提交材料以及缴纳注册费用,所需时间最长为15天。而代注册方式,则需要申请注册报名者从ACCA代表处索取报名表(IRForm)。填写完毕后,申请人员需要将报名表连同以下材料中的部分或全部材料(视各人资历及申请免试等不同情况)一起交到代表处,由代表处汇总整理后寄往英国ACCA总部办理注册手续。注册所需时间一般是在24周,各地区具体时间略有差异。

所需材料:学历/学位证明(本科在校生需要提交学校出具的学生在校证明函)、身份证、英语水平证明、学历课程成绩单(加盖学校公章;本科在校生需要提交所有学年的课程考试的合格成绩单)等证件的原件、复印件和译文以及两张两寸照片、50英镑注册报名费的银行汇票。由于注册所需时间较长,因此小伙伴们在准备材料时一定要注意完整、有效。

另外,注册报名随时都可以进行,但注册时间的早晚,决定了第一次参加考试的时间。比如说,在七月三十一日前注册,有资格参加同年十二月份考试;如果是在十二月十五日前注册,则有资格参加翌年六月份考试。当然了,如果小伙伴们在准备不充分的情况下,51题库考试学习网建议大家还是尽量别急于报考

以上就是关于ACCA学员注册流程的相关情况。51题库考试学习网提醒:代注册和官网注册都有其优势,如果是想尽快完成注册,那么考生最好选择官网注册。最后,51题库考试学习网预祝准备参加2020ACCA考试的小伙伴都能顺利通过。


下面小编为大家准备了 ACCA考试 的相关考题,供大家学习参考。

(c) To correct the problems at Flavours Fine Foods, explain to Alan Jones:

(i) the need for delegation; (3 marks)

正确答案:
(c) (i) Without delegation, formal organisations could not exist. Without allocation of authority, responsibility and delegation, a formal organisation cannot be effective. They are critical aspects. Managers must delegate because of the size and complexity of the organisation (certainly an issue for Flavours Fine Foods). Delegation can help overcome the physical and mental limitations of staff, managers and supervisors and it allows management to attend to other matters since routine tasks and decision making can be passed down. However, superiors must call subordinates to account and coordinate their activities.

Which of the following statements relating to internal and external auditors is correct?

A.Internal auditors are required to be members of a professional body

B.Internal auditors’ scope of work should be determined by those charged with governance

C.External auditors report to those charged with governance

D.Internal auditors can never be independent of the company

正确答案:B

A is incorrect as internal auditors are not required to be members of any professional body. C is incorrect as external auditors report to shareholders rather than those charged with governance. D is incorrect as internal auditors can be independent of the company, if, for example, the internal audit function has been outsourced.


This information was taken from an internal newsletter of The Knowledge Partnership LLP (TKP), a company which offers project and software consultancy work for clients based in Zeeland. The newsletter was dated 2 November 2014 and describes two projects currently being undertaken by the partnership.

Project One

In this project, one of our clients was just about to place a contract for a time recording system to help them monitor and estimate construction contracts when we were called in by the Finance Director. He was concerned about the company supplying the software package. ‘They only have an annual revenue of $5m’, he said, ‘and that worries me.’ TKP analysed software companies operating in Zeeland. It found that 200 software companies were registered in Zeeland with annual revenues of between $3m and $10m. Of these, 20 went out of business last year. This compared to a 1% failure rate for software companies with revenues of more than $100m per year. We presented this information to the client and suggested that this could cause a short-term support problem. The client immediately re-opened the procurement process. Eventually they bought a solution from a much larger well-known software supplier. It is a popular software solution, used in many larger companies.

The client has now asked us to help with the implementation of the package. A budget for the project has been agreed and has been documented in an agreed, signed-off, business case. The client has a policy of never re-visiting its business cases once they have been accepted; they see this as essential for effective cost control. We are currently working with the primary users of the software – account managers (using time and cost data to monitor contracts) and the project support office (using time and cost data to improve contract estimating) – to ensure that they can use the software effectively when it is implemented. We have also given ‘drop in’ briefing sessions for the client’s employees who are entering the time and cost data analysed by the software. They already record this information on a legacy system and so all they will see is a bright new user interface, but we need to keep them informed about our implementation. We are also looking at data migration from the current legacy system. We think some of the current data might be of poor quality, so we have established a strategy for data cleansing (through offshore data input) if this problem materialises. We currently estimate that the project will go live in May 2015.

Project Two

In this project, the client is the developer of the iProjector, a tiny phone-size projector which is portable, easy to use and offers high definition projection. The client was concerned that their product is completely dependent on a specialist image-enhancing chip designed and produced by a small start-up technology company. They asked TKP to investigate this company. We confirmed their fears. The company has been trading for less than three years and it has a very inexperienced management team. We suggested that the client should establish an escrow agreement for design details of the chip and suggested a suitable third party to hold this agreement. We also suggested that significant stocks of the chip should be maintained. The client also asked TKP to look at establishing patents for the iProjector throughout the world. Again, using our customer contacts, we put them in touch with a company which specialises in this. We are currently engaged with the client in examining the risk that a major telephone producer will launch a competitive product with functionality and features similar to the iProjector.

The iProjector is due to be launched on 1 May 2015 and we have been engaged to give advice on the launch of the product. The launch has been heavily publicised, a prestigious venue booked and over 400 attendees are expected. TKP have arranged for many newspaper journalists to attend. The product is not quite finished, so although orders will be taken at the launch, the product is not expected to ship until June 2015.

Further information:

TKP only undertakes projects in the business culture which it understands and where it feels comfortable. Consequently, it does not undertake assignments outside Zeeland.

TKP has $10,000,000 of consultant’s liability insurance underwritten by Zeeland Insurance Group (ZIG).

Required:

(a) Analyse how TKP itself and the two projects described in the scenario demonstrate the principles of effective risk management. (15 marks)

(b) Describe the principle of the triple constraint (scope, time and cost) on projects and discuss its implications in the two projects described in the scenario. (10 marks)

正确答案:

(a) The first stages of risk management are the identification, descriptions and assessment of the risk. This assessment is primarily concerned with the likelihood of them occurring and the severity of impact on the organisation or project should they occur. Sometimes the likelihood is a subjective probability, the opinions of experienced managers or experts in the field. On other occasions, there is some statistical evidence on which to base the assessment. For example, in project 1, TKP identified that 20 IT software companies with annual revenues between $3m and $10m went out of business last year. This represented 10% of the total number of software companies reporting such revenues. Its report to the client suggested that there was a 10% chance of the current preferred supplier (who had a turnover of $5m) ceasing business and this would have a significant short-term support implication. This compared to a business failure rate of 1% for software companies with an annual revenue exceeding $100m. The client felt that the probability of supplier failure was too high, so eventually bought a software solution from a much larger, well-known, software supplier. In this case, the likelihood of the risk led the client to changing its procurement decision. The risk itself does not go away, large companies also fail, but the probability of the risk occurring is reduced.

The avoidance (or prevention) of a risk is a legitimate risk response. In project 1, the client could avoid the risk ‘failure of the supplier’ by commissioning an in-house bespoke solution. Similarly, TKP itself avoids the risks associated with trading in different cultures, by restricting its projects to clients based in Zeeland.

There are three further responses to risks.

Risk mitigation (or risk contingency) actions are what the organisation will do to counter the risk, should the risk take place. Mitigation actions are designed to lessen the impact on the organisation of the risk occurring. In project 2, TKP recommends that the producers of the iProjector should establish an escrow agreement with the company which produces the chip which enhances the quality of the projected image. It was agreed that design details of this chip should be lodged with a third party who would make them available to the producers of the iProjector should the company which owned the enhanced image technology cease trading. This is a mitigation approach to the risk ‘failure of the supplier’. The supplier is relatively high risk (less than three years of trading, inexperienced management team), and the product (the iProjector) is completely dependent upon the supply of the image enhancing chip. The failure of the business supplying the chips would have significant impact on iProjector production. If the escrow agreement had to be enacted, then it would take the producers of the iProjector some time to establish alternative production. Consequently (and TKP have suggested this), it might be prudent to hold significant stocks of the chips to ensure continued production. In such circumstances, the need to mitigate risk is more important than implementing contemporary just-in-time supply practices. In some instances a mitigation action can be put in place immediately. In other instances risk mitigation actions are only enacted should the risk occur. The risk has been recognised and the organisation has a rehearsed or planned response. For example, in project 1, TKP has identified ‘poor quality of current data’ as a risk associated with the migration of data from the current systems to the proposed software package solution. It has established a strategy for data cleansing if that risk actually materialises. Importantly, the client knows in advance how to respond to a risk. It avoids making a hasty, ill-thought out response to an unforeseen event.

Risk transfer actions are concerned with transferring the risk and the assessment and consequences of that risk to another party. This can be done in a number of ways. TKP itself has liability insurance which potentially protects the company from the financial consequences of being sued by clients for giving poor advice. TKP has identified this as a risk, but is unlikely to be able to assess either the probability of that risk occurring or establishing meaningful mitigation measures to minimise the effect of that risk. Consequently, the responsibility for both of these is transferred to an insurance company. They establish the risk, through a series of questions, and compute a premium which reflects the risk and the compensation maximum which will have to be paid if that risk occurs. TKP pays the insurance premiums. TKP itself also transfers risks in project 2. It is unsure about how to establish patents and so it refers the client to another company. Transferring avoids the risk associated with ‘establishing the patent incorrectly’ and the financial consequences of this.

Finally, risk may be identified but just accepted as part of doing business. Risk acceptance is particularly appropriate when the probability of the risk is low or the impact of that risk is relatively insignificant. Risks may also be accepted when there are no realistic mitigation or transfer actions. In project 2, the producers of the iProjector are concerned that there is ‘a risk that a major telephone producer will launch a product with features and functionality similar to ours’. This is a risk, but there is little that can be done about it. Risks of competition are often best accepted.

The discussion above is primarily concerned with deciding what action to take for each risk. Once these actions are agreed, then a plan may be required to put them into place. For example, establishing an escrow agreement will require certain activities to be done.

Risks must also be monitored. For example, in project 2, the risk of supplier failure can be monitored through a company checking agency. Many of these companies offer a continuous monitoring service which evaluates financial results, share prices and other significant business movements. Reports are produced, highlighting factors which may be of particular concern. Risks will also disappear once certain stages of the project have been completed and, similarly, new ones will appear, often due to changes in the business environment. Many organisations use a risk register or risk log to document and monitor risks and such logs often specify a risk owner, a person responsible for adequate management of the risk.

(b) Every project is constrained in some way by its scope, time and cost. These limitations are often called the triple constraint. The scope concerns what has to be delivered by the project, time is when the project should deliver by, and cost is concerned with how much can be spent on achieving the deliverable (the budget). Quality is also an important feature of projects. Some authors include quality in their triple constraint (instead of scope), others add it as a further constraint (quadruple constraint), whilst others believe that quality considerations are inherent in setting the scope, time and cost goals of a project. How a particular project is managed depends greatly on the pressures in the triple constraint.

In project 1, the reluctance of the company to re-visit the business case means that the budget (or cost) of the solution is fixed. The implementation date might be desirable, but it does not seem to be business critical. It is an internal system and so any delays in implementation will not affect customers. It will also be a relatively seamless transition for most employees in the company. They already record the time record details which the new system will collect and so all they will see is a changed user interface. Only the direct users of the output (account managers and the project office) will be affected by any delay. The scope of the software package is also pre-defined. If it fails to meet requirements, then the users will have to adjust their expectations or business methods. There is no money to finance customisation or add-on systems, so in this sense the scope of the solution is also fixed. The quality of the software, in terms of its reliability and robustness, should also be good, as it is a popular software solution used in many large companies.

In project 2, the launch date is fixed. It has been heavily publicised, the venue is booked and over 400 attendees are expected, including newspaper journalists. Thus the time of the project is fixed. However, although orders will be taken at the launch, the product is not expected to ship until a month after launch. Thus the scope of the product shown at the launch date might be restricted and inherent quality problems might not yet be solved. Any defects can be explained away (this is a pre-production model) or, more effectively, they may be avoided by ensuring that the product is demonstrated to attendees, not used by them. The project manager must ensure that key functionality of the product is available on launch date (such as producing an image of a certain quality), but other functionality, not central to the presentation (for example, promised support for all image file formats) could be delayed until after the presentation. The company should make extra funds available to ensure that the launch date is successful.


声明:本文内容由互联网用户自发贡献自行上传,本网站不拥有所有权,未作人工编辑处理,也不承担相关法律责任。如果您发现有涉嫌版权的内容,欢迎发送邮件至:contact@51tk.com 进行举报,并提供相关证据,工作人员会在5个工作日内联系你,一经查实,本站将立刻删除涉嫌侵权内容。