The most crucial time for project risk assessment is ( ).
A
when a problem surfaces
B
during the planning phase
C
during the close-out phase
D
after the project schedule has been published
参考答案
参考解析
解析:
进行项目风险评估最关键的时候是:规划阶段
A:问题出现时
B:规划阶段
C://结束阶段
D://项目进度公布后
更多 “单选题The most crucial time for project risk assessment is ( ).A when a problem surfacesB during the planning phaseC during the close-out phaseD after the project schedule has been published” 相关考题
考题
The technique most commonly used to determine the profitability of a project includes _____ methods.A . Net present value (NPV).B . Return on investment (ROI).C . Discounted cash flow (DCF)D . Payout time and risk sensitivity analysis.E . All of the above.
考题
"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .A be completed in reduced overall time than other projects.B be in a higher risk category than other projects.C not be compatible with project risk and assessmentD A and BE All of the above.
考题
Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D
考题
The schedule risk is the _____ .A the accumulated "expected' durations which maintain project completion.B Critical Path adjusted by "high-risk" activity float.C highest risk path that maintains quality.D Critical Path when calculated with "most likely" duration.E highest risk path that contributes the most risk toward the project completion.
考题
Amount at Stake is the _____ .A function of planned time/real time project costs.B risk identified in successful project completions.C (Standard Project Deviation + Expected Costs)/6D cost of investment loss + least cost to restore status quo.E inherent risk at conception altered by standard project deviations.
考题
The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .A Is accomplished by paying the actual costs to the contractor.B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).C Is an undisclosed contingency in the contractor's bid.D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.E B and C
考题
Which of the following actions is an example of risk response:A adjust project parameters (scope, time, quality ...)B reduce the probability of potential project risk eventsC reduce the consequences of potential project risk eventsD wait until a problem actually happens, then deal with it in the most effective and efficient manner.E A, B and C only
考题
It is useful to conduct project risk assessment according to the project'sA charterB statement of workC Work Breakdown structureD networkE budget
考题
Risk management allows the project manager and the project team to:A eliminate most risks during the planning phase of the projectB identify project risksC identify impacts of various risksD plan suitable responsesE B, C and D only
考题
111 It is useful to conduct project risk assessment according to the project'sA. charterB. statement of workC. Work Breakdown structureD. networkE. budget
考题
115 The technique most commonly used to determine the profitability of a project includes _____ methods.A. Net present value (NPV).B. Return on investment (ROI).C. Discounted cash flow (DCF)D. Payout time and risk sensitivity analysis.E. All of the above
考题
23 Which of the following actions is an example of risk response:A. adjust project parameters (scope, time, quality ...)B. reduce the probability of potential project risk events C. reduce the consequences of potential project risk eventsD. wait until a problem actually happens, then deal with it in the most effective and efficient manner.E. A, B and C only
考题
93 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .A. Is accomplished by paying the actual costs to the contractor.B. Is accomplished by paying the contractor for his costs plus a fixed fee (profit).C. Is an undisclosed contingency in the contractor's bid.D. Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.E. B and C
考题
112 The schedule risk is the _____ .A. the accumulated "expected' durations which maintain project completion.B. Critical Path adjusted by "high-risk" activity float.C. highest risk path that maintains quality.D. Critical Path when calculated with "most likely" duration.E. highest risk path that contributes the most risk toward the project completion
考题
170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D
考题
178 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .A. be completed in reduced overall time than other projects.B. be in a higher risk category than other projects.C. not be compatible with project risk and assessmentD. A and BE. All of the above
考题
105 Which of the following actions is an example of risk response:A. adjust project parameters (scope, time, quality ...)B. reduce the probability of potential project risk eventsC. reduce the consequences of potential project risk eventsD. wait until a problem actually happens, then deal with it in the most effective and efficient manner.E. A, B and C only
考题
3 Project tradeoffs are usually made by comparing _____ and constraints.A. Time, cost, and qualityB. Time, risk, and qualityC. Risk, quality, and manpower availabilityD. Cost, quality, and technical performanceE. Cost, quality, and risk
考题
● Project tradeoffs are usually made by comparing _____ and constraints.A Time, cost, and qualityB Time, risk, and qualityC Risk, quality, and manpower availabilityD Cost, quality, and technical performanceE Cost, quality, and risk
考题
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan
考题
______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan
考题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
考题
The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB
The most crucial time for project risk assessment is (75) .A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published
考题
A key activity in closing out a project is to(47).A.Disseminate status reports and risk assessment.B.Disseminate information to formalize project completion.C.Monitor the specific project results to determine if they comply with relevant quality standards.D.Transfer all the project records to the project owners.
考题
The most crucial time for project risk assessment is ( ).A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published
考题
The most crucial time for project risk assessment is ( ) . A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
考题
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan
热门标签
最新试卷