The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A
Riskldentification
B
Quantitative RiskAnalysis
C
Qualitative RiskAnalysis
D
Risk Monitoring and Control
参考答案
参考解析
解析:
该题的关键词为"analyzes the effect of risk, numerical rating",其语句结构为"The()一process(主语)analyzes(谓语)the effect of risk events(宾语)and assigns(并列谓语)anumerical rating to those risks(并列宾语)",含义为"什么过程分析风险事件的后果,并且为这些风险指定数值级别",容易判断题目描述的是量化风险分析的特点,应该选择选项B。
更多 “单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A RiskldentificationB Quantitative RiskAnalysisC Qualitative RiskAnalysisD Risk Monitoring and Control” 相关考题
考题
Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.
考题
Risk mitigation is the process of _____ .A transferring risk to another party.B reducing uncertainty on the projectC identifying all possible risk eventsD monitoring status and making adjustmentsE All of the above.
考题
Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D
考题
Screening of risk events for potential risk is known as _____ .A problem structuring.B risk identificationC risk quantificationD risk modelingE risk mitigation
考题
Risk event probability is defined as:A the total number of possible events divided into the expectations or frequency of the risk eventB the number of times the risk event may occurC the fraction of the total project tasks which may be affected by the risk eventD the total number of possible events divided into the consequences of the risk event.E A and B
考题
Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.
考题
15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events
考题
108 Project Risk Management is based on which of the following premises:A. the future is unknown.B. unknowns can result in risks or opportunities.C. we cannot control risk events.D. project risk impact can be measured and controlledE. All of the above
考题
113 Screening of risk events for potential risk is known as _____ .A. problem structuring.B. risk identificationC. risk quantificationD. risk modelingE. risk mitigation
考题
170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D
考题
26 Risk mitigation is the process of _____ .A. transferring risk to another party.B. reducing uncertainty on the projectC. identifying all possible risk eventsD. monitoring status and making adjustmentsE. All of the above.
考题
108 Risk mitigation is the process of _____ .A. transferring risk to another party.B. reducing uncertainty on the projectC. identifying all possible risk eventsD. monitoring status and making adjustmentsE. All of the above
考题
______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan
考题
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
Workarounds are determined during which risk management process? (75).A. Risk identificationB. Quantitative risk analysisC. Plan risk responsesD. Risk monitoring and control
考题
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management
考题
The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring anD.Control
考题
( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
考题
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、RiskldentificationB、Quantitative RiskAnalysisC、Qualitative RiskAnalysisD、Risk Monitoring and Control
考题
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control
考题
单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A
RiskldentificationB
Quantitative RiskAnalysisC
Qualitative RiskAnalysisD
Risk Monitoring and Control
考题
单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A
Risk IdentificationB
Quantitative Risk AnalysisC
Qualitative Risk AnalysisD
Risk Monitoring and Control
考题
单选题The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A
RiskldentificationB
Quantitative Risk AnalysisC
Qualitative Risk AnalysisD
Risk Monitoring and Control
热门标签
最新试卷