网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Risk Identification

B.Quantitative Risk Analysis

C.Qualitative Risk Analysis

D.Risk Monitoring and Control


参考答案

更多 “ The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control ” 相关考题
考题 ● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control

考题 Project Risk _____ .A should not be calculated for small projects.B is the probability of each risk event minus the sum of the consequences of potential risk events.C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D cannot be quantified for first time projects.E B or D

考题 Screening of risk events for potential risk is known as _____ .A problem structuring.B risk identificationC risk quantificationD risk modelingE risk mitigation

考题 Risk event probability is defined as:A the total number of possible events divided into the expectations or frequency of the risk eventB the number of times the risk event may occurC the fraction of the total project tasks which may be affected by the risk eventD the total number of possible events divided into the consequences of the risk event.E A and B

考题 Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.

考题 15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events

考题 144 Risk event probability is defined as:A. the total number of possible events divided into the expectations or frequency of the risk eventB. the number of times the risk event may occurC. the fraction of the total project tasks which may be affected by the risk eventD. the total number of possible events divided into the consequences of the risk event.E. A and B

考题 113 Screening of risk events for potential risk is known as _____ .A. problem structuring.B. risk identificationC. risk quantificationD. risk modelingE. risk mitigation

考题 170 Project Risk _____ .A. should not be calculated for small projects.B. is the probability of each risk event minus the sum of the consequences of potential risk events.C. is the cumulative effect of uncertain occurrences which will adversely affect project objectives.D. cannot be quantified for first time projects.E. B or D

考题 You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

考题 A situation in which one of two or more risk events will follow an act, but the precise nature of these events maynot be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:a. Certaintyb. Uncertaintyc. Riskd. Risk adversitye. None of the above

考题 The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control

考题 ●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline

考题 The(30)process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

考题 When you think of the Internet, you probably think of ".com." Just what do those three letters at the end of a World Wide Web address mean? Every computer that hosts data on the Internet has a(71)numerical address. For example, the numerical address for the White House is 198.137.240.100. But since(72)people want to remember long strings of numbers, the(73)was developed. It is a critical part of the Internet's technical infrastructure, correlates a numerical address to a word. To(74)the White House website, you could type its numerical address into the address box of your web browser. But most people prefer to use "www. whitehouse. gov." In this case, the domain name is(75).A.uniqueB.isolatedC.similarD.same

考题 Workarounds are determined during which risk management process? (75).A. Risk identificationB. Quantitative risk analysisC. Plan risk responsesD. Risk monitoring and control

考题 Which software process sorts client login requests and assigns them to a virtual router for RADIUS service?() A.PPPB.AAAC.LCPD.NCP

考题 ()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management

考题 The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control

考题 You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.

考题 The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

考题 The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、RiskldentificationB、Quantitative RiskAnalysisC、Qualitative RiskAnalysisD、Risk Monitoring and Control

考题 The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control

考题 Which software process sorts client login requests and assigns them to a virtual router for RADIUS service?()A、PPPB、AAAC、LCPD、NCP

考题 单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future project performance.C This process assigns cost estimates for expected future period operating costs.D The cost baseline is the expected cost for the project.

考题 单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A Risk IdentificationB Quantitative Risk AnalysisC Qualitative Risk AnalysisD Risk Monitoring and Control

考题 单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A RiskldentificationB Quantitative RiskAnalysisC Qualitative RiskAnalysisD Risk Monitoring and Control

考题 单选题Most parents encourage their children to take an active part in social events,()those events do not interfere with their studies.A lestB thoughC unlessD provided