网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
- A、Riskldentification
- B、Quantitative Risk Analysis
- C、Qualitative Risk Analysis
- D、Risk Monitoring and Control
参考答案
更多 “ The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A、RiskldentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control” 相关考题
考题
● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk Analysis.Risk Monitoring and Control
考题
Project Risk Management is based on which of the following premises:A the future is unknown.B unknowns can result in risks or opportunities.C we cannot control risk events.D project risk impact can be measured and controlledE All of the above.
考题
Total project risk can be defined as:A the sum of the probabilities of project risks events times the sum of consequences of those risksB the sum of the products of each project risk event times its consequencesC the sum of the consequences of all project risk eventsD the sum of the probabilities of all project risk eventsE 1 - the sum of the probabilities of all project risk events.
考题
15 Total project risk can be defined as:A. the sum of the probabilities of project risks events times the sum of consequences of those risksB. the sum of the products of each project risk event times its consequencesC. the sum of the consequences of all project risk eventsD. the sum of the probabilities of all project risk eventsE. 1 - the sum of the probabilities of all project risk events
考题
108 Project Risk Management is based on which of the following premises:A. the future is unknown.B. unknowns can result in risks or opportunities.C. we cannot control risk events.D. project risk impact can be measured and controlledE. All of the above
考题
●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan
考题
______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan
考题
The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control
考题
●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).(73)A. project management planB. project baselineC. risk response planD. risk baseline
考题
Workarounds are determined during which risk management process? (75).A. Risk identificationB. Quantitative risk analysisC. Plan risk responsesD. Risk monitoring and control
考题
The (72) process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Quantitative Risk AnalysisB.Risk IdentificationC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.A.Identity risksB.Control risksC.Plan risk responsesD.Plan risk management
考题
The______process ascertains which risks have the potential Of affecting the proect and documenting the risks' characteristics.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
The(75)process analyzes the effect of risk events and assigns a numerical rating to those risks.A.Risk IdentificationB.Quantitative Risk AnalysisC.Qualitative Risk AnalysisD.Risk Monitoring and Control
考题
()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risks
B.monitor risks
C.implement risks responses
D.plan risk management
考题
Managing risk and documenting them is very important in project planning process.You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the(73) .A.project management plan
B.project baseline
C.riskresponse plan
D.risk baseline
考题
May be involved in the qualitative analysis of project risks(). A.Establish probability and influence matrix
B.Decision tree analysis
C.Sensitivity analysis
D.Modeling and simulation
考题
The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics. A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring anD.Control
考题
( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、RiskldentificationB、Quantitative RiskAnalysisC、Qualitative RiskAnalysisD、Risk Monitoring and Control
考题
()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan
考题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A、Risk IdentificationB、Quantitative Risk AnalysisC、Qualitative Risk AnalysisD、Risk Monitoring and Control
考题
单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A
RiskldentificationB
Quantitative RiskAnalysisC
Qualitative RiskAnalysisD
Risk Monitoring and Control
考题
单选题The()process analyzes the effect of risk events and assigns a numerical rating to those risks.A
Risk IdentificationB
Quantitative Risk AnalysisC
Qualitative Risk AnalysisD
Risk Monitoring and Control
考题
单选题The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.A
RiskldentificationB
Quantitative Risk AnalysisC
Qualitative Risk AnalysisD
Risk Monitoring and Control
考题
单选题()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A
Quantitative Risk AnalysisB
Qualitative Risk AnalysisC
Enterprise Environmental FactorsD
Risk Management Plan
热门标签
最新试卷