考题
The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation
考题
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.
考题
The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A.Conceptual, charter/baseline.B.Conceptual, master schedule.C.Development, charter/baseline.D.Development, master schedule.E.Development, masterplan.
考题
When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.A . Reduce features and/or functionalityB . Increase risk.C . Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)D . All of the above.E . A and B only
考题
The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:A post project evaluationB post contract evaluationC post mortemD procurement performance evaluationE contractor's performance evaluation
考题
181 The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:A. post project evaluationB. post contract evaluationC. post mortemD. procurement performance evaluationE. contractor's performance evaluation
考题
11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.A. Reduce features and/or functionalityB Increase risk.C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)D. All of the above.E. A and B only
考题
41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation
考题
● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
●Ravi, like many project (71) ,had studied the waterfall model of software development as the primary software life-cycle (72) .He was all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (73) and not as (74) .The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice.To be the most suitable, an existing process must be (75) to the new problem.Adevelopment process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.(71) A.customers B.managers C.users D.administrators(72) A.activity B.procedure C.process D.progress(73) A.parts B.modules C.software D.a whole(74) A.parts B.modules C.software D.a whole(75) A.modified B.used C.suited D.tailored
考题
The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB
The most crucial time for project risk assessment is (75) .A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published
考题
There is nothing in this world constant butinconstancy. —SWIFT Project after project designs a set of algorithms and thenplunges into construction of customer-deliverable software on a schedule thatdemands delivery of the first thing built.?In most projects, the first system built is(71) usable. Itmay be too slow, too big, awkward to use, or all three. There is no (72) but to startagain, smarting but smarter, and build a redesigned version in which theseproblems are solved. The discard and (73) may be done in one lump, or it may be done piece-by-piece. But alllarge-system experience shows that it will be done. Where a new system conceptor new technology is used, one has to build a system to throw away, for eventhe best planning is not so omniscient (全知的) as to get it right the first time.The management question, therefore, is notwhether to build a pilot system and throw it away. You will do that. The onlyquestion is whether to plan in advance to build a (74) , or topromise to deliver the throwaway to customers. Seen this way, the answer ismuch clearer. Delivering that throwaway to customers buys time, but it does soonly at the (75) of agony (极大痛苦)for the user, distraction for the builders while they do theredesign, and a bad reputation for the product that the best redesign will findhard to live down.Hence plan to throw one away; you will,anyhow.(71)A.almostB.oftenC.usuallyD.barely
考题
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resourceA.work breakdown structureB.baselineC.software requirements specificationD.plan
考题
The most crucial time for project risk assessment is ( ).A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published
考题
hich factors must be most considered when developing acceptance creteria?( )A.Match with requirements B.User availability C.Ablity to benchmark system D.Schedule of system delivery
考题
Which factors must be most considered when developing acceptance criteria(72)A.Match with requirementsB.User availabilityC.Ability to benchmark systemD.Schedule of system delivery
考题
There is nothing in this world constant but inconstancy.-SWIFT
Project after project designs a set of algorithms and then plunges into construction of customer-deliverable software on a schedule that demands delivery of the first thing built.
In most projects,the first system built is(请作答此空)usable.It may be too slow,too big,awkward to use,or all three.There is no( )but to start again,smarting but smarter,and build a redesigned version in which these problems are solved.The discard and( )may be done in one lump,or it may be done piece-by-piece.But all large-system experience shows that it will be done.Where a new system concept or new technology is used,one has to build a system to throw away,for even the best planning is not so omniscient(全知的)as to get it right the first time.
The management question,therefore,is not whether to build a pilot system and throw it away.You will do that.The only question is whether to plan in advance to build a______,or to promise to deliver the throwaway to customers.Seen this way,the answer is much clearer.Delivering that throwaway to customers buys time,but it does SO only at the( )of agony(极大痛苦)for the user,distraction for the builders while they do the redesign,and a bad reputation for the product that the best redesign will find hard to live down.
Hence plan to throw one away;you will,anyhow.A.almost
B.often
C.usually
D.barely
考题
An example of scope verification is ( ).A.review the performance of an installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceeD.with the project
考题
The most crucial time for project risk assessment is ( ) . A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
考题
Before a project schedule can be created,the schedule maker should have a ( ) ,an effort estimate for each task,and a resource list with availability for each resource.A.work breakdown structure
B.baseline
C.software requirements specification
D.plan
考题
Ravi, like many project (1) , had studied the waterfall model of software development as the primary software life-cycle (2) . He has all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (3) and not as (4) . The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice. To be the most situation, an existing process must be (5) to the new problem. A development process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.
空白(5)处应选择()A、modifiedB、usedC、suitedD、tailored
考题
The most crucial time for project risk assessment is ( ).A、when a problem surfacesB、during the planning phaseC、during the close-out phaseD、after the project schedule has been published
考题
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)
考题
单选题When will Premier make their first payment?A
Upon delivery of the computers.B
Thirty days after delivery.C
Two months after delivery.
考题
单选题The most crucial time for project risk assessment is ( ).A
when a problem surfacesB
during the planning phaseC
during the close-out phaseD
after the project schedule has been published
考题
单选题The first and most important thing parents should do to help their children is _____.A
to provide them with a safer environmentB
to lower their expectations for themC
to get them more involved sociallyD
to set a good model for them to follow