考题
The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user
考题
Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A.The project manager and project office personnel.B.The project team and functional managers.C.The project sponsor.D.All of the above.E.A and B only.
考题
Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .A . Project managers; team membersB . Company management philosophy in treating employees; the average workerC . Project sponsors; project managersD . The functional team; project sponsorsE . Recruitment policy; wage and salary administration
考题
Expectancy theory as applied to project management implies that:A The team will work the hardest on those goals that are clearly explained by the project managerB The more rewards that the project manager provides, the better the performance of the teamC Team members will work hardest for those project goals that also bring satisfaction to personal goalsD Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team membersE None of the above
考题
108 The way a project manager sends and receives information depends upon:A. How others relate to the project managerB. The project manager's level in the organizational hierarchyC. the size and nature of the projectD. the project manager's salary and ageE. the number of projects going on at one time in the company
考题
145 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A. The project manager and project office personnel.B. The project team and functional managers.C. The project sponsor.D. All of the above.E. A and B only
考题
174 In a matrix organizational form, MBO may be difficult to implement:A. If the functional employees are supervised closely by the line manager rather than the project managerB. Unless the project manager has an input into the employee's performance review C. Unless the project and line managers agree on the ultimate objectiveD. Unless the project and line managers agree to the duration of the taskE. None of the above are correct answers
考题
189 Ouchi's Theory Z relates more to _____ whereas Theory X / Theory Y relates to _____ .A. Project managers; team membersB. Company management philosophy in treating employees; the average workerC. Project sponsors; project managersD. The functional team; project sponsorsE. Recruitment policy; wage and salary administration
考题
123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user
考题
38 Expectancy theory as applied to project management implies that:A. The team will work the hardest on those goals that are clearly explained by the project managerB. The more rewards that the project manager provides, the better the performance of the teamC. Team members will work hardest for those project goals that also bring satisfaction to personal goalsD. Employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team membersE. None of the above
考题
● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user
考题
● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A The project manager and project office personnel.B The project team and functional managers.C The project sponsor.D All of the above.E A and B only.
考题
●To ensure the project team provides the functionality the customerexpects in a new piece of software, the project manager ask the customer forsign-off on the design criteria. These documents are(75).(75) A. technical specificationsB. performance specificationsC. product descriptionsD. quality assurance
考题
The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter
考题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
考题
The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders
考题
The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performancIf a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The (73) provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.project charterC.project human resource planD.project stakeholders
考题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
考题
Earned value management(EVM)integrates the scope baseline with the()baseline,along with schedule baseline,to form the performance,which helps the project management team assess and measure project performance and progress.A.qulity
B.risk
C.change
D.cost
考题
The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter
考题
The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter
考题
单选题The()provides the project manager with the authority to apply organizational resources to project activities.A
project management planB
contractC
project human resource planD
projectcharter
考题
单选题The()provides the project manager with the authority to apply organizational resources to project activities.A
project management planB
contractC
project human resource planD
project charter