Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule
B.activity list
C.project charter
D.project schedule
参考答案
参考解析
解析:计划进展需要对持续时间和资源的评估和修改创建一个被核准的(74),它可以作为基线,有助于跟踪进展。A.范围说明B.活动列表C.项目章程 D.项目计划
更多 “Schedule development can require the review and revision of duration estimates and resource estimates to create an approved () that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule ” 相关考题
考题
The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation
考题
The project scope/charter baseline includes:A.Summary of background conditions defining the project.B.Organization, authority and responsibility relationships.C.Functions to be performed.D.Resource requirement schedule including time estimates.E.All of the above.
考题
During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.B.Is still the original baseline but annotated to reflect that a change has taken place.C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.Is the same since baseline schedules cannot change once the development phase is completed.
考题
Managerial Reserves are:A.allowances to account for price changes that can occur over the life of a project.B.incentive fees paid to managers for good performance.C.funds used to offset poor cost or schedule estimates.D.accounts to allocate and maintain funds for contingency programsE.All of the above.
考题
Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above
考题
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E. Is the same since baseline schedules cannot change once the development phase is completed
考题
41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
考题
123 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not providedE. All of the above are possible based upon the situation
考题
● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation
考题
● The project scope/charter baseline includes:A Summary of background conditions defining the project.B Organization, authority and responsibility relationships.C Functions to be performed.D Resource requirement schedule including time estimates.E All of the above.
考题
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.time estimatingB.cost estimatingC.project planningD.schedule development
考题
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend
考题
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend
考题
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
考题
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.(74)A.scope statementB.activity listC.project charterD.project schedule
考题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule
考题
On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A.project planningB.time estimatingC.cost estimatingD.schedule development
考题
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.A.scope statementB.activity listC.project charterD.project schedule
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
考题
Developing the project schedule is often an
iterative process. It determines the planned start and finish dates for project
activities and milestones. Schedule development can require the review and
revision of duration estimates and resource estimates to create an approved
project schedule that can serve as a baseline to ( ) progress. A.analyze
B.track
C.level
D.extenD.
考题
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.A、time estimatingB、cost estimatingC、project planningD、schedule development
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating
考题
Which of the following objects can be directly referenced by a window object?()A、 Schedule objectB、 Program objectC、 Job objectD、 Resource planE、 Resource consumer group
考题
单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A
analyzeB
trackC
levelD
extend
考题
单选题On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.A
time estimatingB
cost estimatingC
project planningD
schedule development
考题
单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A
activity duration estimating, schedule developing, activity resource estimatingB
activity resource estimating, activity duration estimating, schedule developmentC
schedule developing, activity resource estimating, activity duration estimatingD
activity resource estimating, schedule developing, activity duration estimating
热门标签
最新试卷