The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A
costaggregation
B
reserve analysis
C
parametricestimating
D
funding limit reconciliation
参考答案
参考解析
解析:
可以注意到该题的关键词为"mathematical model"和"predict total project cost",再划分语句结构"The()technique(主语)involves(谓语)using project characteristics in a mathematical model to predict total project cost",易理解语句含义为"什么技术使用数学模型预测项目的总成本"。观察四个选项,ABD也可能应用数学模型,也可能只是简单的数字规定,但选项C 一定会应用数学模型,所以应该选择parametric estimating。
更多 “单选题The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.A costaggregationB reserve analysisC parametricestimatingD funding limit reconciliation” 相关考题
考题
Most project management leadership theories focus on all of the following except:A . Personal characteristics of the project managerB . The situation at handC . Personal traits of the subordinatesD . Behavioral styles of the project managerE . Usefulness of authority and power in leadership
考题
Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:A . Performing feasibility studiesB . Proposal preparationC . being close to the customerD . MaturityE . None of the above are universal characteristics
考题
A project manager can exchange information with the project team using which media?A tactileB audioC olfactoryD visualE All of the above.
考题
Monte Carlo simulation:A Was originally developed by Dr. CarloB Is a European technique for assessing project risksC assumes the future risk events will occur at random according to predetermined probability distributionsD is a technique to stimulate create risk event resolutionE A, B and C only
考题
27 Monte Carlo simulation:A. Was originally developed by Dr. CarloB. Is a European technique for assessing project risksC. assumes the future risk events will occur at random according to predetermined probability distributionsD. is a technique to stimulate create risk event resolutionE. A, B and C only
考题
136 Universal characteristics of effective project managers include such skills as communication, decision-making, planning, ability to identify problems and:A. Performing feasibility studiesB. Proposal preparationC. being close to the customerD. MaturityE. None of the above are universal characteristics
考题
71 Most project management leadership theories focus on all of the following except:A. Personal characteristics of the project managerB. The situation at handC. Personal traits of the subordinatesD. Behavioral styles of the project managerE. Usefulness of authority and power in leadership
考题
In the project management context()includes characteristics of unification,consolidation, articulation, and integrative actions that are crucial to project completion,successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter
考题
The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.
A.costaggregationB.reserve analysisC.parametricestimatingD.funding limit reconciliation
考题
● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.A.integrationB.scopeC.processD.charter
考题
The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.A.Cost AggregationB.Reserve AnalysisC.Parametric EstimatingD.Funding Limit Reconciliation
考题
A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram
考题
● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition
考题
● A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called (72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide (73) , whose purpose is to contain the various pieces of relevant information – feasibility assessments, schedules, needs analysis, and so forth – in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management. (74) was developed to make clear the interdependence between project tasks before those tasks are scheduled. (75) offers the advantage of clearly showing overlapping tasks.
考题
( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.A.Critical path method(CPM)B.Earned value management(EVM)C.Net present value method (NPVM)D.Expert judgment method(EIM)
考题
Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables
考题
The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.A.reserve analysisB.cost aggregationC.parametric estimatingD.funding limit reconciliation
考题
In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development
考题
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.A.ParametricB.AnalogousC.Three-pointD.Expert judgment
考题
A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Functional decomposition diagram
B.Work Breakdown Structure
C.Structure Chart
D.Organizational Structure
考题
()is a technique for estimating the duration or cost of activity or a projecy using historical data orm a similar activity or project.A.Analogous estimating
B.Parametric estimating
C.Three-Point estmating
D.Bottom-Up estimating
考题
The () technique involves using project characteristics in a mathematical modelto predict total project costs. Models can be simple or complex. A.Cost Aggregation
B.Reserve Analysis
C.ParametriC.Estimating
D.Funding Limit Reconciliation
考题
( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project. A.Parametric
B.Analogous
C.Three-point
D.Expert judgment
考题
Which of the following techniques is used for tracking the project risks?()A、Probability-Impact matrixB、Pareto chartC、R-ChartD、PERT (Program Evaluation and Review Technique) analysis
考题
单选题The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A
Evaluate phase exit milestones using sufficiency criteriaB
Flexible entry and exit criteria to minimize schedule delaysC
Quality measures reported only to the project steering committeeD
Many work teams with few members to maximize the number of deliverable hand-offs