网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
单选题
They went _____ the schedule for the conference again and again until they felt satisfied with every detail of it.
A
out
B
up
C
over
D
by
参考答案
参考解析
解析:
句意:他们一遍又一遍的查看会议时间表,直到他们对每个细节都满意了为止。go over查看,重温。go out出去。go up向上。go by路过。
句意:他们一遍又一遍的查看会议时间表,直到他们对每个细节都满意了为止。go over查看,重温。go out出去。go up向上。go by路过。
更多 “单选题They went _____ the schedule for the conference again and again until they felt satisfied with every detail of it.A outB upC overD by” 相关考题
考题
What is the relative priority of project Cost, Schedule and Quality?A . 1)Cost - 2)Schedule - 3)QualityB . 1)Quality - 2)Schedule - 3)CostC . 1)Quality - 2)Cost - 3)ScheduleD . 1)Schedule - 2)Quality - 3)CostE . All are of equal priority
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
"he never went there again, nor __________ to apologize."
A. he writesB.he wroteC. did he writeD. does he write
考题
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating
考题
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method
考题
- Where shall we have the meeting -()
A、In the first conference room.B、The first conference room is spacious.C、The first conference room isn’t good.
考题
There was a sudden gust of wind and ____.
A、went away his hatB、went his hat awayC、away went his hatD、away his hat went
考题
Where shall we have the meeting?()A. The first conference room is spaciousB. The first conference room isn't goodC. In the first conference room
考题
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )A.fast trackingB.what-if scenario analysisC.resource levelingD.critical chain method
考题
Questions 55-56 refer to the following e-mail.
To: Marketing Department
From: Federico Botella
Date: January9
Subject: Sales Meeting.
We need to postpone the sales meeting that I had arranged for January 15. I have a meeting
with a client in Cancun on January 14, and I was not able to get a flight back to Houston until January 16. I'm sorry for any inconvenience this may cause you. The meeting is now tentatively rescheduled for 9 A.M. on January 18 in the conference room.
What is the purpose of this e-mail?
A. To schedule a conference.
B. To reschedule a meeting.
C. To introduce a new client.
D. To announce vacation plans.
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
考题
Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking
B.what-if scenario analysis
C.resource leveling
D.critical chain methoD.
考题
Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain methoD.
考题
Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain methoD.
考题
A:Where shall we have the meeting? B:()AThe first conference room is spaciousBThe first conference room isn't goodCIn the first conference room
考题
A:Where shall we have the meeting? B:()A、The first conference room is spaciousB、The first conference room isn't goodC、In the first conference room
考题
You are helping the customer customer configure anthentication,a new asyncOS upgradebecomes available,what should you do?() A、avoid mentioning the upgrade to the customerB、schedule a convenient time to upgrade again, backing up the configuration before and after theupgradeC、contact customer support and ask them to run the upgrade for youD、immediately show the customer how to run the CLI command upgrade
考题
You are the network administrator for All servers run Windows Server 2003. You are creating a backup schedule for the main file server. You need to create a schedule so that backup jobs are completed in the shortest amount of time possible. What should you do?()A、Schedule a normal backup every Sunday. Schedule incremental backups every Monday through Saturday.B、Schedule a normal backup every Sunday. Schedule differential backups every Monday through Saturday.C、Schedule a copy backup every day.D、Schedule a normal backup every day.
考题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating
考题
You have an Exchange Server 2010 organization. You plan to provide users with the ability to schedule meetings. You need to recommend a scheduling solution that meets the following requirements: .Ensures that users can schedule conference rooms for meetings .Ensures that conference room owners can change the settings of meetings scheduled by users What should you include in the solution?()A、Managed Folder AssistantB、public foldersC、resource mailboxesD、room list distribution groups
考题
单选题When a student said Resterday I goed to see a fiend of mine', which of the following ways for correcting errors is NOT encouraged?A
Oh, yes.I see you went to see a friend of yours.B
You goed to see your friend?C
No, not goed. You should say went.D
Say it again, please.
考题
单选题Derek: Have you seen the film Olive Twist, Kathy? Kathy: yes, I went last night. ______ Derek: Saw it Monday. Good, isn’t it? Kathy: Mm, it made me want to read the novel again.A
How are things going? B
How about you?C
How nice!D
How disappointing!
考题
单选题They went ______ the schedule for the conference again and again until they felt satisfied with every detail of it.A
outB
upC
overD
by
考题
单选题Please give Jim the schedule for tomorrow’s conference when he _____ back. He is to chair the conference.A
will comeB
comeC
comesD
came
考题
问答题Practice 3 On July 10th the company will hold its first worldwide video conference(电视会议). All twenty facilities will be linked by a satellite broadcasting system so that employees can see and speak with each other. Mr. Black will begin the conference by telling us about our goals for the next five years. Next, each manager will speak about current challenges. The last hour will be devoted to questions from all locations. If it proves successful, we hope to schedule worldwide video conferences annually.
考题
单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A
activity duration estimating, schedule developing, activity resource estimatingB
activity resource estimating, activity duration estimating, schedule developmentC
schedule developing, activity resource estimating, activity duration estimatingD
activity resource estimating, schedule developing, activity duration estimating
热门标签
最新试卷