网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project
参考答案
参考解析
解析:项目整合管理包括在项目管理过程组中识别、定义、组合、统一和协调各种过程和项目管理活动的过程和活动。识别项目风险过程不属于项目整合管理。
A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。
A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。
更多 “Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.A.Developing project charter B.Developing project management plan C.Analyzing project risks D.Monitoring and controlling project” 相关考题
考题
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.(71)A. projectB. project management teamC. performing organizationD. customer
考题
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A.ProjectB.project management teamC.performingorganizationD.customer
考题
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.(74)A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
考题
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.tA.IntegrationB.ScopeC.ConfigurationD.Requiremen
考题
● The inputs of developing project management plan do not include (72).(72)A. project charterB. stakeholder management strategyC. project scope statementD. outputs from planning processes
考题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.A.Develop ScheduleB.Estimate Activity ResourcesC.Define ActivitiesD.Sequence Activities
考题
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)(75)A. Project Scope StatementB. Project Management PlanC. ForecastsD. Project Charter
考题
The inputs of developing project management plan do not include (72) .A.project charterB.stakeholder management strategyC.project scope statementD.outputs from planning processes
考题
The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter
考题
The( )provides the project manager with the authority to apply organizational resources to project activities。A.project management planB.project charterC.project human resource planD.project stakeholders
考题
Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.A.Developing project charterB.Developing project management planC.Analyzing project risksD.Monitoring and controlling project
考题
Project Quality Management processes include all the activities of the (75) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.A.performing organizationB.project management teamC.projectD.customer
考题
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A.IntegrationB.ScopeC.ConfigurationD.Requirement
考题
The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75).A.Project Scope StatementB.Project Management PlanC.ForecastsD.Project Charter
考题
In project time management processes,( )involves identifying and documenting the relationships between project activities.A.activity definitionB.activity sequencingC.schedule controlD.Schedule development
考题
The Develop Project Management Plan Process includes the actions necessary to define, prepare,integrate, and coordinate all constituent plans into a ( )A. Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter
考题
The inputs of developing project management plan do not include()A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE
B:Project stakeholder management
C:Project scope management
D:Project cost management
考题
A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.task
B.work
C.sequence
D.activity
考题
The inputs of developing project management plan do not include (). A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes
考题
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE
B. Project stakeholder management
C. Project scope management
D. Project cost management
考题
The inputs of developing project management plan do not include()A、project charterB、stakeholder management strategyC、project scope statementD、outputs from planning processes
考题
The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter
考题
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A、ProjectB、project management teamC、performingorganizationD、customer
考题
The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、projectcharter
考题
Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.A、IntegrationB、ScopeC、ConfigurationD、Requirement
考题
单选题Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A
ProjectB
project management teamC
performingorganizationD
customer
热门标签
最新试卷