The intention of the__(75)__is to schedule,organize and control all activities to achieve the project goal eventually.No matter how difficult it is and what kind of risks are ther
A.
B.project work breakdown
C.project security authentication
D.project management
E.project flowchart
参考答案
更多 “ The intention of the__(75)__is to schedule,organize and control all activities to achieve the project goal eventually.No matter how difficult it is and what kind of risks are therA.B.project work breakdownC.project security authenticationD.project managementE.project flowchart ” 相关考题
考题
Documented work authorization provide:A.a means of effective internal coordination of the project's activities.B.an audit trail of all work authorized from project initiation to completion.C.a means for communication of work activity between the project manager and the performing activities.D.All of the aboveE.A and B only.
考题
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.
考题
Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.
考题
A Project Status Report would include all of the following except:A Cost and schedule reportsB Changes to scope. cost or scheduleC Narrative explanation of variancesD Personnel problems on the projectE Upcoming activities
考题
Project managers must know:A What kind of message to sendB to whom to send the messageC how to translate the message into a language that everyone can understandD All of the aboveE A and B only
考题
In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A Work breakdown structureB milestone review and schedule techniqueC cost/schedule control systemD planning programming budget systemE program and evaluation review technique
考题
142 Project managers must know:A. What kind of message to sendB. to whom to send the messageC. how to translate the message into a language that everyone can understandD. All of the aboveE. A and B only
考题
171 Documented work authorization provide:A. a means of effective internal coordination of the project's activities.B. an audit trail of all work authorized from project initiation to completionC.a means for communication of work activity between the project manager and the performing activities.D. All of the aboveE. A and B only
考题
178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A. Work breakdown structureB. milestone review and schedule techniqueC. cost/schedule control systemD. planning programming budget systemE. program and evaluation review technique
考题
● A project is defined as:A a coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance.B a large, complex undertaking with many objectives, multiple sources of funding, and a not discernible end point.C an undertaking of interrelated activities directed toward a specific goal that can be accomplished in less than one year.D a group of activities headed by a project manager who has cradle-to-grave cycle responsibility for the end product.E All of the above.
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.
考题
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend
考题
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend
考题
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .(73)A. measure, delay, record, distribute, analyze, and directB. plan, schedule, monitor, control, report, and forecastC. promote, highlight, monitor, control, forecast, and reportD. emphasize, visualize, analyze, conceptualize, report, and record
考题
The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.A.project work breakdownB.project security authenticationC.project managementD.project flowchart
考题
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such , the schedule is used by the project management team to()A.Measure, delay, record, distribute, analyze, and direct
B.Plan, schedule, monitor, control, report, and forecast
C.Promote, highlight, monitor, control, forecast, and report
D.Emphasize, visualize, analyze, conceptualize, report and record
考题
The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.A.Cost control
B.Schedule control
C.Change control
D.Risk control
考题
( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.A.Schedule forecasts
B.Schedule compression
C.Change requests
D.Data analysis
考题
The intention of the ( ) is to schedule,organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there. A.project work breakdown
B.project security authentication
C.project management
D.project flowchart
考题
The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter
B.project scope goal
C.project budget
D.project scope statement
考题
The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.A、project work breakdownB、project security authenticationC、project managementD、project flowchart
考题
What is the goal of the borderless network architecture?()A、to provide users with A single device that permits access to information anywhereB、to provide users with the same productivity and access to information no matter where are or which device they useC、to eliminate the need for border security and firewallsD、to provide companies with A way to extend their security and control over employees on the internet
考题
What is the goal of the borderless network architecture?()A、to provide users withA single device that permits access to information anywhereB、to provide users with the same productivity and access to information no matter where are or which device they useC、to eliminate the need for border security and firewallsD、to provide companies withA way to extend their security and control over employees on the internet
考题
The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)
考题
单选题What is the goal of the borderless network architecture?()A
to provide users with A single device that permits access to information anywhereB
to provide users with the same productivity and access to information no matter where are or which device they useC
to eliminate the need for border security and firewallsD
to provide companies with A way to extend their security and control over employees on the internet
考题
单选题What is the goal of the borderless network architecture?()A
to provide users withA single device that permits access to information anywhereB
to provide users with the same productivity and access to information no matter where are or which device they useC
to eliminate the need for border security and firewallsD
to provide companies withA way to extend their security and control over employees on the internet