网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
The leader ordered that the task_____________ as soon as possible.
A、finishes
B、is finished
C、finish
D、be finished
参考答案
更多 “ The leader ordered that the task_____________ as soon as possible.A、finishesB、is finishedC、finishD、be finished ” 相关考题
考题
In the PDM, common constraints include:A.Start-to-startB.Finish-to-startC.Finish-to-finishD.B and C onlyE.A, B, and C.
考题
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start
考题
By the time Robert()writing the first draft of his paper, most of the other students will be completing their final draft.A、finishesB、has finishedC、finishedD、finishing
考题
PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish
考题
Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
热门标签
最新试卷