(请给出正确答案)
is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
参考答案
更多 “ is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。A.Planned valueB.Actual costC.Earned valueD.Cost variance ” 相关考题
考题
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.
考题
The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A . Multiplying the actual hours worked on the project by the budgeted labor rate.B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.C . Dividing the actual hours required to complete the task by the budgeted labor rate.D . Cannot be determined.E . None of the above
考题
During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.
考题
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A. Multiplying the actual hours worked on the project by the budgeted labor rate.B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.C. Dividing the actual hours required to complete the task by the budgeted labor rate.D. Cannot be determined.E. None of the above
考题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.PlannedvalueB.Earned valueC.ActualcostD.Costvariance
考题
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A.estimatingB.definingC.planningD.sequencing
考题
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing
考题
is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A.Planned valueB.Earned valueC.Actual costD.Cost variance
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.(74)A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
考题
A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements listA.EssencesB.ElementsC.PurposesD. Issues
考题
A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list. A.Essences
B.Elements
C.Purposes
D.Issues
考题
()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period。 A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
考题
( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.A.Schedule forecasts
B.Schedule compression
C.Change requests
D.Data analysis
考题
The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance
B.Schedule Variance
C.EarneD.Value
D.Cost PerformeD.Index
考题
The advantage of rail transport is ()A、Great amount of shippedB、Less damage rationC、Fast speed, exact schedule, and cost savedD、Direct shipping line
考题
You are the network administrator for All servers run Windows Server 2003. You are creating a backup schedule for the main file server. You need to create a schedule so that backup jobs are completed in the shortest amount of time possible. What should you do?()A、Schedule a normal backup every Sunday. Schedule incremental backups every Monday through Saturday.B、Schedule a normal backup every Sunday. Schedule differential backups every Monday through Saturday.C、Schedule a copy backup every day.D、Schedule a normal backup every day.
考题
单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A
Planned valueB
Earned valueC
Actual costD
Cost variance
考题
单选题() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A
projectacceptanceB
scopeverificationC
scopedefinitionD
WBS Creation
考题
单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.A
PlannedvalueB
Earned valueC
ActualcostD
Costvariance
考题
单选题You are the network administrator for All servers run Windows Server 2003. You are creating a backup schedule for the main file server. You need to create a schedule so that backup jobs are completed in the shortest amount of time possible. What should you do?()A
Schedule a normal backup every Sunday. Schedule incremental backups every Monday through Saturday.B
Schedule a normal backup every Sunday. Schedule differential backups every Monday through Saturday.C
Schedule a copy backup every day.D
Schedule a normal backup every day.
考题
单选题His hard-working spirit attracted and activated others. As a result, the work was completed ahead of schedule.A
strove for B
stirred up C
stripped awayD
stretched out
热门标签
最新试卷