网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
单选题
A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()
A
Order a new HMC to support the p5 system.
B
Attach the new p5 system to the existing HMC.
C
Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.
D
Do nothing. This system does not require an HMC.
参考答案
参考解析
解析:
暂无解析
更多 “单选题A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()A Order a new HMC to support the p5 system.B Attach the new p5 system to the existing HMC.C Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.D Do nothing. This system does not require an HMC.” 相关考题
考题
A financial customer has three data centers that are approximately five kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds between the three sites.Which of the following solutions satisfies the customer‘s recovery time objective?()A. DS8700 systems at each site running Metro MirrorB. DS5300 systems at each site running Metro MirrorC. DS5100 systems at each site running Global MirrorD. XIV systems at each site running synchronous mirroring
考题
A customer has many RS/6000s and POWER4 systems running different AIX applications. What should the customer do to best position themselves for the migration to POWER5?()A、Upgrade OS to AIX 5.2.B、Implement Micro-Partitioning.C、Upgrade HMC to support POWER5.D、Install Partition Load Manager.
考题
A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server. What is the minimum PowerVM edition that supports the customer requirement?()A、 PowerVM Lx86B、 PowerVM Express EditionC、 PowerVM Standard EditionD、 PowerVM Enterprise Edition
考题
A customer has ordered a rack, a p650, two p630s, and two p615s. During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit. However, the specialist knows that the p650 will be racked, but the other systems will arrive separately. In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()A、Because additional systems would require more power receptaclesB、Because the customer may need to do additional facilities planningC、Because the customer needs additional funding to cover the servicesD、Because postponing the eventual discussion will likely lead to customer dissatisfaction
考题
What IBM resource helps to easily identify a business application that has been validated on IBM Systems?() NOTE:// Solutions that are in this resource represent applications that enable IBM Systems and verify, through customer experience, installing and running in a customer location.A、IBM Standalone Solutions Configuration Tool (SSCT)B、IBM Server ProvenC、IBM System x Reference Sheets (xREF)D、IBM Sizing Guides
考题
A prospective customer has a SCSI installed. The new project requires a large high performance storage and tape network . The customer does not appear to understand the terminology and options of the fiber channel components of the solution. Further discussion confirms that the customers only has cursory knowledge of fiber channel and is not currently prepared to for the installation. What steps should be taken to make sure customer is satisfied with the solution? ()A、Suggest a cloud networkB、Direct the customer to redbooks and white papers on FC technologiesC、Work with business partner to include Lab Service engagement to setup FC environment and perform knowledge transferD、Switch project to iSCSI
考题
A customer wants to expand their current storage environment, but has floor space for only two machine frames or two racks. Their environment consists of IBM SAN Volume Controllers and IBM DS4000 systems. The DS4000 systems are at end of lease. The customer wants the maximum number of disks possible in two frames. Which of the following solutions is best for this customer?()A、add one SVCB、install one DS8700C、install one DS8800D、install one XIV system
考题
A customer needs to deploy ten dual processor Xeon servers. Six servers will be running Linux and Apache, and the other four will be Citrix presentation servers. The customer’s main concerns are the rack space and the option to have SATA drives. The maximum memory required is 8GB. Which of the following options will provide the best price and performance?()A、Ten x306’s with internal SATA drivesB、Five x346’s with internal SATA drives and VMWare ESX ServerC、Five x366’s partitioned into two VMs each with VMWare ESX ServerD、Ten x336’s with internal SATA drives
考题
A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment. Which of the following questions would most impact the memory configuration?()A、What version of VMWare ESX Server is being considered?B、Do the systems currently use Double Data Rate (DDR) memory?C、What is the total number of processors installed in the production systems?D、What is the total amount of memory currently being used across all the production systems?
考题
A customer has two DS8000 systems in their environment. One DS8000 has FlashCopy licensed while the other does not. The customer wishes to license FlashCopy on the second DS8000. Which of the following describes the TDA requirement in this situation()A、a pre-sale TDA is mandatoryB、a pre-install TDA is mandatoryC、a pre-install TDA is not mandatory since it is not FirstIn Customer Location (FICL)D、both pre-sale and pre-install TDAs are mandatory
考题
A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them. Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()A、The technical support specialist has completed a UNIX course at college.B、The technical specialist has supported several similar projects and has earned an IBM AIX certification.C、The technical support specialist’s company sells $3M of UNIX computer systems every year.D、The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.
考题
Companycom is considering a large partitioned p5 590 to consolidate several smaller systems in their data center. Due to the complexity of the consolidation, the customer is asking the technical support specialist to give them a report which shows pre order PCI adapter placement and validates them against IBM's recommendations. The concern is that the factory will not install the adapters in the appropriate slots as the customer pre-selected. What IBM tool is available to provide this?()A、LPAR Validation Tool (LVT)B、Personal Systems Configurator (PSC)C、IBM Configuration for eBusiness (eConfig)D、Advanced System Management Interface (ASMI)
考题
A customer has 12 x445s and 20 x365s in their datacenter that are dedicated to production workloads. The customer wants to standardize on IBM Director as their Intel environment systems management platform. Which server platform is supported as a Director server?()A、zSeriesB、pSeriesC、iSeriesD、iSeries with IXA Adapter
考题
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()A、Purchase a second HMC and use this to manage the new servers.B、Connect all of the new servers to the existing private HMC network.C、Configure a second private network on their existing HMC for the new servers.D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.
考题
A customer currently has a large group of older 1U servers. Each dedicated to aunique application. Quick provisioning of the servers is important to the customer. Which of the following approaches addresses this situation?()A、VirtualizationB、Replace each server with energy efficient serversC、Upgrade in place to improve performanceD、Implement BladeCenter
考题
A customer currently has five partitioned POWER4 systems and is adding new systems. When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()A、Order a new HMC to support the p5 system.B、Attach the new p5 system to the existing HMC.C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.D、Do nothing. This system does not require an HMC.
考题
The customer has an older storage array and is looking to migrate data that currently exists onover 100 73 GB FC drives to a new IBM System Storage DS5020. The customer states that theyhave only 3 TB of data and wants to consolidate on to fewer higher capacity drives. There are sixapplication servers running multiple applications and operating systems utilizing the storagesystem. What would be the next step to accurately identify the new storage configuration?()A、initiate a Disk Magic studyB、initiate a Capacity Magic studyC、runiometer on the current environmentD、utilize the IBM Disk capacity planner toolkit
考题
A financial customer has three data centers that are four kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds. Which solution satisfies the customer’s recovery time objective()A、DS8700 systems at each site running Metro MirrorB、DS8700 systems at each site running Global MirrorC、DS5300 systems at each site running Global MirrorD、XIV systems at each site running Remote Mirroring
考题
A financial customer has three data centers that are approximately five kilometers apart. Their SAP application data needs to be kept synchronized within 10 milliseconds between the three sites. Which of the following solutions satisfies the customer's recovery time objective?()A、DS8700 systems at each site running Metro MirrorB、DS5300 systems at each site running Metro MirrorC、DS5100 systems at each site running Global MirrorD、XIV systems at each site running synchronous mirroring
考题
A customer has a Stock Watch application that publishes stock recommendations to different customers and programs. The stock recommendation message should be processed by only one of the JMS Servers in the cluster. Which JMS model should be used?()A、JMS QueueB、Distributed JMS QueueC、Uniform Distributed TopicD、Partitioned Distributed Topic
考题
单选题A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()A
IBM CPWB
IBM rPerfC
SPECint_rate2006D
IDEAS International RPE2
考题
单选题A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them. Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()A
The technical support specialist has completed a UNIX course at college.B
The technical specialist has supported several similar projects and has earned an IBM AIX certification.C
The technical support specialist’s company sells $3M of UNIX computer systems every year.D
The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.
考题
单选题A customer has an existing rack environment with 18 x365 and 2 x255 servers. How can the customer monitor and manage the hardware even if the systems are shut down?()A
Use PC Anywhere over the Ethernet LAN.B
Use RDM and Aurema to manage the systems.C
Connect high-speed modems to each of the systems’ serial ports to use IBM Director.D
Interconnect the Remote Supervisor Adapters II (RSA II) in the x365 servers to the x255 servers.
考题
单选题A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers. The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server. How can the specialist help the customer?()A
Explain to the customer that they need an additional HMC for the POWER5 system.B
Obtain a PO from the customer to purchase additional serial connections to the HMC.C
Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.D
Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
考题
单选题A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server. What is the minimum PowerVM edition that supports the customer requirement?()A
PowerVM Lx86B
PowerVM Express EditionC
PowerVM Standard EditionD
PowerVM Enterprise Edition
考题
单选题The pSeries sales representative has done an excellent job in educating the customer on the benefits of working with IBM. The customer is planning to implement their first ERP application. This new application will be critical to running their business. The customer has only a competitor’s UNIX systemcurrently installed. They are interested in obtaining a proposal from IBM. In addition to the AIX hardware and HACMP software, what else should be included in the IBM proposal for the new ERP solution?()A
I/T services and education to help with the implementation of the hardware and softwareB
A Supportline specialist to work directly with the customer to manage any issues that ariseC
The services required to move the currently installed applications from the competitor’s systems to the IBM systemsD
A slimmed down solution to ensure that the IBM solution is less expensive than the competitor’s solution
热门标签
最新试卷