( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart

参考答案

参考解析
解析:甘特图是一类描述项目进度的图表。它说明了一个项目的开始和结束时间。A.甘特图 B.项目直方图C.里程碑图 D.项目流程图
更多 “( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. A.gantt chart B.project histogram C.milestone chart D.project flowchart ” 相关考题
考题 ● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.

考题 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

考题 ●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

考题 Difficult _____ the project was, I managed to finish it on schedule. A: no matterB: asC: despiteD: though

考题 ● A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for(72) .(72)A.identifying individual tasks for a projectB.scheduling the start of tasksC.scheduling the end of tasksD.determining potential delays

考题 A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart

考题 In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter

考题 A__(74)__is a type of bar chart that illustrates a project schedulA.It illustrates the start and finish dates of the terminal elements and summary elements of a project.B.Gantt chartC.project histogramD.milestone chartE.project flowchart

考题 Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables

考题 In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

考题 Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule

考题 A schedule is commonly used in project planning and project portfolio management.(73) on a schedule may be closely related to the work breakdown structure(WBS)terminal elements.the statement of work.or a contract data requirements listA.EssencesB.ElementsC.PurposesD. Issues

考题 line chart窗口3的信息来自于哪个地方() A.chart 1的 additional infoB.chart 1的 eventC.chart 1的 change msD.chart 1的Information Elements

考题 Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan B.risk management C.scope management plan D.management schedule

考题 A schedule is commonly used in project planning and project portfolio management. ( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list.时间表常用于项目规划和项目组合管理。时间表的元素与工作分解结构(WBS)的最终元素( ),工作说明书,或合同数据需求清单密切相关。A.Essences精髓 B.Elements元素 C.Purposes目的 D.Issues问题

考题 In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.schedule B.activity C.Plan D.contractor

考题 A schedule is commonly used in project planning and project portfolio management.( ) on a schedule may be closely related to the work breakdown structure (WBS)terminal elements, the statement of work, or a contract data requirements list. A.Essences B.Elements C.Purposes D.Issues

考题 Define Activities is the process of identifying the specific actions to be performed to produce the ( ) . A.project elements B.work drafts C.work package D.project deliverables

考题 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress. A.analyze B.track C.level D.extenD.

考题 Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element. A.relationships B.resources C.stakeholders D.deliverables

考题 ()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart

考题 line chart窗口3的信息来自于哪个地方() A、chart 1的 additional infoB、chart 1的 eventC、chart 1的 change msD、chart 1的Information Elements

考题 Project Quality Management must address the management of the project and the()ofthe project. While Project Quality Management applies to all projects,regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A、performanceB、processC、productD、object

考题 单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A scheduleB activityC planD contractor

考题 单选题Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A performanceB processC productD object

考题 单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A analyzeB trackC levelD extend

考题 填空题David will go on holiday as soon as he (finish) ____ the project.