网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
单选题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A
Plannedvalue
B
Earned value
C
Actualcost
D
Costvariance
参考答案
参考解析
解析:
该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。
更多 “单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.A PlannedvalueB Earned valueC ActualcostD Costvariance” 相关考题
考题
The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?A.Time, schedule and cost.B.Management coordination and organization structuring.C.Work methods and accountability.D.Quality of work.E.Risk and impact decision-making.
考题
The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A . Multiplying the actual hours worked on the project by the budgeted labor rate.B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.C . Dividing the actual hours required to complete the task by the budgeted labor rate.D . Cannot be determined.E . None of the above
考题
During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.
考题
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A. Multiplying the actual hours worked on the project by the budgeted labor rate.B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.C. Dividing the actual hours required to complete the task by the budgeted labor rate.D. Cannot be determined.E. None of the above
考题
163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A. The project will be completed late.B. The critical path has been lengthened.C. the costs are being overrun.D. Overtime will be required to maintain the original critical path.E. None of the above.
考题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.PlannedvalueB.Earned valueC.ActualcostD.Costvariance
考题
● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.
考题
● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?A Time, schedule and cost.B Management coordination and organization structuring.C Work methods and accountability.D Quality of work.E Risk and impact decision-making.
考题
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.A.estimatingB.definingC.planningD.sequencing
考题
is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A.Planned valueB.Earned valueC.Actual costD.Cost variance
考题
The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned
考题
The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date
考题
Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary
考题
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
考题
The work breakdown structure (WBS) has been widely used in management for software development project, ( ) is generally NOT validated through the WBS.A.Schedule and costB.Organization structuringC.Management coordinationD.Quality of work
考题
is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。A.Planned valueB.Actual costC.Earned valueD.Cost variance
考题
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
考题
()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period。 A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
考题
In project time management processes, ( )involves identifying and documenting the relationships between project activities.A.activity definition
B.activity sequencing
C.schedule control
D.schedule development
考题
The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance
B.Schedule Variance
C.EarneD.Value
D.Cost PerformeD.Index
考题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.A、PlannedvalueB、Earned valueC、ActualcostD、Costvariance
考题
Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating.
空白(2)处填()A、activityB、workC、currencyD、time
考题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A、Planned valueB、Earned valueC、Actual costD、Cost variance
考题
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A、estimatingB、definingC、planningD、sequencing
考题
单选题()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.A
Planned valueB
Earned valueC
Actual costD
Cost variance
考题
单选题The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.A
estimatingB
definingC
planningD
sequencing
考题
单选题The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.A
estimatingB
definingC
planningD
sequencing
热门标签
最新试卷