网友您好, 请在下方输入框内输入要搜索的题目:
题目内容
(请给出正确答案)
() is one of the quality planning outputs.
- A、Scope base line
- B、Cost of quality
- C、Product specification
- D、Quality checklist
参考答案
更多 “ () is one of the quality planning outputs.A、Scope base lineB、Cost of qualityC、Product specificationD、Quality checklist” 相关考题
考题
The key ingredient to a successful quality management program are _____.A . management's quality philosophy, operational quality assurance and operational quality control.B . quality evaluation methods and functional quality integrators.C . technical quality administration, the technical quality specifications, and the quality process review.D . quality evaluation methods, quality progress reviews and the technical quality specifications.E . All of the above.
考题
● The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not (72 ).(72)A. executed inB. inspected inC. check-inD. look-in
考题
87 The key ingredient to a successful quality management program are _____.A. management's quality philosophy, operational quality assurance and operational quality control. B. quality evaluation methods and functional quality integrators.C. technical quality administration, the technical quality specifications, and the quality process review. D. quality evaluation methods, quality progress reviews and the technical quality specifications.E. All of the above
考题
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A.BenchmarkingB.Quality metricC.Quality checklistD.Brainstornung
考题
● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data
考题
● (75)is one of the quality planning outputs.(75)A. Scope base lineB. Cost of qualityC. Product specificationD. Quality checklist
考题
According to the principles or the six key points proposed by Harvard Business School to judge the quality of an elevator pitch, it may be inferred that the example given in lesson five could be a defective one.()
考题
●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.(71)A. BenchmarkingB. Quality metricC. Quality checklistD. Brainstorming
考题
Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data
考题
is one of the quality planning outputs.A.Scope base lineB.Cost of qualityC.Product specificationD.Quality checklist
考题
is one of the quality planning outputs. A.Scope base line B.Cost ofquality C.Product specification D.Quality checklist
考题
● Project()is an uncertain event or condition that ,if it occurs ,has a positive or a negative effect on at least one project objective ,such as time ,cost ,scope or quality()A. risk B. problem C. result D. data
考题
The project team members should also be aware of one of the fundamental tenets of modem quality management: quality is planned, designed and built in, not(72).A.executed inB.inspected inC.check-inD.look-in
考题
Do you think that the quality of the product is superior ___ that one’s?
A.thanB.aboveC.overD.to
考题
Software quality assurance is now an(71)sub-discipline of software engineering. As Bucldy and Oston point out,(72)software quality assurance is likely to lead to an ultimate(73)of software costs. However, the major hurdle in the path of software management in this area is the lack of(74)software standards. The development of accepted and generally applicable standards should be one of the principal goals of(75)in software engineering.A.emergingB.emergentC.engagingD.evolve
考题
Generally speaking, quality inspection is ( ) of visual inspection and interior inspection.
A. composed B. each
C. one D. result
考题
()is one of the quality planning outputs. A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist
考题
According to the maxim of ( ) suggested by Grice, one should speak truthfully. A.quality
B.manner
C.relation
D.quantity
考题
The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()A、executedinB、inspectedinC、check-inD、look-in
考题
Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.A、BenchmarkingB、Quality metricC、Quality checklistD、Brainstorming
考题
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A、BenchmarkingB、Quality metricC、Quality checklistD、Brainstornung
考题
单选题According to the author, happiness lies in the ability to ______.A
think of something extraordinaryB
experience delight at an old ageC
feel the magic quality of pleasureD
enjoy what one has at the moment
考题
单选题According to the passage,we can see that lower prices and better quality occur______.A
as a result of the effect of one on the otherB
always at the same timeC
independently of each otherD
when the demand exceeds the supply
考题
单选题() is one of the quality planning outputs.A
Scope base lineB
Cost of qualityC
Product specificationD
Quality checklist
考题
单选题Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.A
BenchmarkingB
Quality metricC
Quality checklistD
Brainstornung
考题
单选题Quality planning tools are often used to help plan effective quality management activities.( ) is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.A
BenchmarkingB
Quality metricC
Quality checklistD
Brainstorming
考题
单选题The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()A
executedinB
inspectedinC
check-inD
look-in
热门标签
最新试卷